Onshore wind project GI-83, Randolph County Onshore wind |
1,018 MW | Agreement signed |
Randolph, MO | Southeast |
Jun 2019 | target 2027 |
Other project J1490, Randolph County Other |
1,000 MW | Agreement signed |
Randolph, MO | MISO |
Apr 2019 | target 2024 |
Other project J1488, Randolph County Other |
500 MW | Agreement signed |
Randolph, MO | MISO |
Apr 2019 | target 2024 |
Gas project GI-121, Randolph County Gas |
460 MW | Agreement signed |
Randolph, MO | Southeast |
May 2024 | target 2030 |
Gas project GI-101, Clinton County Gas |
460 MW | Agreement signed |
Clinton, MO | Southeast |
Jul 2022 | target 2027 |
Onshore wind project J1026, Audrain County Onshore wind |
400 MW | Agreement signed |
Audrain, MO | MISO |
Mar 2018 | target 2023 |
Solar project GEN-2017-108, Henry County Solar |
400 MW | Agreement signed |
Henry, MO | SPP |
Aug 2017 | target 2027 |
Onshore wind project J1025, Knox County Onshore wind |
300 MW | Agreement signed |
Knox, MO | MISO |
Mar 2018 | target 2025 |
Solar project J1145, Callaway County Solar |
250 MW | Agreement signed |
Callaway, MO | MISO |
Mar 2018 | target 2024 |
Onshore wind project GI-95, Dade County Onshore wind |
247 MW | Agreement signed |
Dade, MO | Southeast |
Dec 2020 | target 2026 |
Onshore wind project J476, Atchison County Onshore wind |
246 MW | Agreement signed |
Atchison, MO | MISO |
Sep 2015 | target 2021 |
Solar project GI-120, Randolph County Solar |
245 MW | Agreement signed |
Randolph, MO | Southeast |
Apr 2024 | target 2031 |
Onshore wind project GI-53, Nodaway County Onshore wind |
238 MW | Agreement signed |
Nodaway, MO | Southeast |
May 2016 | target 2018 |
Onshore wind project GI-61, Nodaway County Onshore wind |
230 MW | Agreement signed |
Nodaway, MO | Southeast |
May 2017 | target 2019 |
Solar project J956, Ralls County Solar |
200 MW | Agreement signed |
Ralls, MO | MISO |
Mar 2018 | 2024 |
Solar project GEN-2019-016, Polk County Solar |
200 MW | Agreement signed |
Polk, MO | SPP |
Apr 2019 | target 2029 |
Solar project GEN-2020-088, Jasper County Solar |
150 MW | Agreement signed |
Jasper, MO | SPP |
Apr 2020 | target 2028 |
Solar project J1268, Lincoln County Solar |
150 MW | Agreement signed |
Lincoln, MO | MISO |
Apr 2019 | target 2023 |
Solar + storage project GEN-2020-072, Henry County Solar + storage |
150 MW | Agreement signed |
Henry, MO | SPP |
Apr 2020 | target 2029 |
Solar project GEN-2017-188, Barry County Solar |
130 MW | Agreement signed |
Barry, MO | SPP |
Nov 2017 | target 2026 |
Solar project GI-86, Randolph County Solar |
100 MW | Agreement signed |
Randolph, MO | Southeast |
Oct 2019 | target 2027 |
Solar project J1352, Montgomery County Solar |
100 MW | Agreement signed |
Montgomery, MO | MISO |
Apr 2019 | target 2024 |
Solar project GI-93, Macon County Solar |
100 MW | Agreement signed |
Macon, MO | Southeast |
Nov 2020 | target 2026 |
Solar project GI-90, Randolph County Solar |
100 MW | Agreement signed |
Randolph, MO | Southeast |
Jul 2020 | target 2027 |
Solar project GI-91, Carroll County Solar |
96.0 MW | Agreement signed |
Carroll, MO | Southeast |
Jul 2020 | target 2027 |
Gas project GI-102, Clinton County Gas |
75.0 MW | Agreement signed |
Clinton, MO | Southeast |
Jul 2022 | target 2027 |
Gas project GEN-2020-064, Jasper County Gas |
64.0 MW | Agreement signed |
Jasper, MO | SPP |
Apr 2020 | 2025 |
Hydro project J1213, Iron County Hydro |
60.0 MW | Agreement signed |
Iron, MO | MISO |
Apr 2019 | target 2024 |
Battery storage project GEN-2018-031, Jackson County Battery storage |
50.0 MW | Agreement signed |
Jackson, MO | SPP |
May 2018 | target 2028 |
Battery storage project GEN-2021-042, Jackson County Battery storage |
50.0 MW | Agreement signed |
Jackson, MO | SPP |
Apr 2021 | target 2028 |
Gas project GI-117, New Madrid County Gas |
46.0 MW | Agreement signed |
New Madrid, MO | Southeast |
May 2023 | target 2024 |
Gas project GEN-2020-061, Cass County Gas |
29.0 MW | Agreement signed |
Cass, MO | SPP |
Apr 2020 | target 2026 |
Gas project GI-116, New Madrid County Gas |
26.0 MW | Agreement signed |
New Madrid, MO | Southeast |
May 2023 | target 2024 |
Onshore wind project GI-60, Gentry County Onshore wind |
18.0 MW | Agreement signed |
Gentry, MO | Southeast |
Apr 2017 | |