Projects with signed interconnection agreements in Missouri

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown347,888 MW
Active in queue29.7 GW124 requests
Agreement signed7,888 MW34 requests
Withdrawn25251.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

34 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GI-83, Randolph County
Onshore wind
1,018 MWAgreement signed Randolph, MOSoutheast Jun 2019target 2027
Other project J1490, Randolph County
Other
1,000 MWAgreement signed Randolph, MOMISO Apr 2019target 2024
Other project J1488, Randolph County
Other
500 MWAgreement signed Randolph, MOMISO Apr 2019target 2024
Gas project GI-121, Randolph County
Gas
460 MWAgreement signed Randolph, MOSoutheast May 2024target 2030
Gas project GI-101, Clinton County
Gas
460 MWAgreement signed Clinton, MOSoutheast Jul 2022target 2027
Onshore wind project J1026, Audrain County
Onshore wind
400 MWAgreement signed Audrain, MOMISO Mar 2018target 2023
Solar project GEN-2017-108, Henry County
Solar
400 MWAgreement signed Henry, MOSPP Aug 2017target 2027
Onshore wind project J1025, Knox County
Onshore wind
300 MWAgreement signed Knox, MOMISO Mar 2018target 2025
Solar project J1145, Callaway County
Solar
250 MWAgreement signed Callaway, MOMISO Mar 2018target 2024
Onshore wind project GI-95, Dade County
Onshore wind
247 MWAgreement signed Dade, MOSoutheast Dec 2020target 2026
Onshore wind project J476, Atchison County
Onshore wind
246 MWAgreement signed Atchison, MOMISO Sep 2015target 2021
Solar project GI-120, Randolph County
Solar
245 MWAgreement signed Randolph, MOSoutheast Apr 2024target 2031
Onshore wind project GI-53, Nodaway County
Onshore wind
238 MWAgreement signed Nodaway, MOSoutheast May 2016target 2018
Onshore wind project GI-61, Nodaway County
Onshore wind
230 MWAgreement signed Nodaway, MOSoutheast May 2017target 2019
Solar project J956, Ralls County
Solar
200 MWAgreement signed Ralls, MOMISO Mar 20182024
Solar project GEN-2019-016, Polk County
Solar
200 MWAgreement signed Polk, MOSPP Apr 2019target 2029
Solar project GEN-2020-088, Jasper County
Solar
150 MWAgreement signed Jasper, MOSPP Apr 2020target 2028
Solar project J1268, Lincoln County
Solar
150 MWAgreement signed Lincoln, MOMISO Apr 2019target 2023
Solar + storage project GEN-2020-072, Henry County
Solar + storage
150 MWAgreement signed Henry, MOSPP Apr 2020target 2029
Solar project GEN-2017-188, Barry County
Solar
130 MWAgreement signed Barry, MOSPP Nov 2017target 2026
Solar project GI-86, Randolph County
Solar
100 MWAgreement signed Randolph, MOSoutheast Oct 2019target 2027
Solar project J1352, Montgomery County
Solar
100 MWAgreement signed Montgomery, MOMISO Apr 2019target 2024
Solar project GI-93, Macon County
Solar
100 MWAgreement signed Macon, MOSoutheast Nov 2020target 2026
Solar project GI-90, Randolph County
Solar
100 MWAgreement signed Randolph, MOSoutheast Jul 2020target 2027
Solar project GI-91, Carroll County
Solar
96.0 MWAgreement signed Carroll, MOSoutheast Jul 2020target 2027
Gas project GI-102, Clinton County
Gas
75.0 MWAgreement signed Clinton, MOSoutheast Jul 2022target 2027
Gas project GEN-2020-064, Jasper County
Gas
64.0 MWAgreement signed Jasper, MOSPP Apr 20202025
Hydro project J1213, Iron County
Hydro
60.0 MWAgreement signed Iron, MOMISO Apr 2019target 2024
Battery storage project GEN-2018-031, Jackson County
Battery storage
50.0 MWAgreement signed Jackson, MOSPP May 2018target 2028
Battery storage project GEN-2021-042, Jackson County
Battery storage
50.0 MWAgreement signed Jackson, MOSPP Apr 2021target 2028
Gas project GI-117, New Madrid County
Gas
46.0 MWAgreement signed New Madrid, MOSoutheast May 2023target 2024
Gas project GEN-2020-061, Cass County
Gas
29.0 MWAgreement signed Cass, MOSPP Apr 2020target 2026
Gas project GI-116, New Madrid County
Gas
26.0 MWAgreement signed New Madrid, MOSoutheast May 2023target 2024
Onshore wind project GI-60, Gentry County
Onshore wind
18.0 MWAgreement signed Gentry, MOSoutheast Apr 2017

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)