United States β€Ί Grid β€Ί Interconnection queues β€Ί Minnesota

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Minnesota (2022 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown183,583 MW
Active in queue5,142 MW31 requests
Agreement signed0.0 MW0 requests
Withdrawn183,583 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

18 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project J2624, Stevens County
Battery storage
450 MWWithdrawn / abandoned Stevens, MNMISO Sep 2022target 2026
Battery storage project J2492, Wilkin County
Battery storage
300 MWWithdrawn / abandoned Wilkin, MNMISO Sep 2022target 2024
Battery storage project J2419, Faribault County
Battery storage
300 MWWithdrawn / abandoned Faribault, MNMISO Sep 2022target 2027
Battery storage project J2569, St. Louis County
Battery storage
300 MWWithdrawn / abandoned St. Louis, MNMISO Sep 2022target 2026
Onshore wind project J3125, Cottonwood County
Onshore wind
289 MWWithdrawn / abandoned Cottonwood, MNMISO Sep 2022target 2027
Solar project J2600, Wabasha County
Solar
245 MWWithdrawn / abandoned Wabasha, MNMISO Sep 2022target 2026
Solar + storage project J2598, Mower County
Solar + storage
198 MWWithdrawn / abandoned Mower, MNMISO Sep 2022target 2026
Battery storage project J2652, Dakota County
Battery storage
197 MWWithdrawn / abandoned Dakota, MNMISO Sep 2022target 2026
Solar project J3025, Douglas County
Solar
188 MWWithdrawn / abandoned Douglas, MNMISO Sep 2022target 2027
Onshore wind project J3020, Lyon County
Onshore wind
165 MWWithdrawn / abandoned Lyon, MNMISO Sep 2022target 2027
Onshore wind project J3029, Freeborn County
Onshore wind
153 MWWithdrawn / abandoned Freeborn, MNMISO Sep 2022target 2026
Solar project J2433, Wadena County
Solar
150 MWWithdrawn / abandoned Wadena, MNMISO Sep 2022target 2027
Solar project J2748, Clearwater County
Solar
150 MWWithdrawn / abandoned Clearwater, MNMISO Sep 2022target 2026
Battery storage project J2872, Dakota County
Battery storage
150 MWWithdrawn / abandoned Dakota, MNMISO Sep 2022target 2025
Solar project J2863, Fillmore County
Solar
125 MWWithdrawn / abandoned Fillmore, MNMISO Sep 2022target 2027
Solar project J2420, Faribault County
Solar
95.0 MWWithdrawn / abandoned Faribault, MNMISO Sep 2022target 2027
Solar + storage project J2760, Hubbard County
Solar + storage
68.0 MWWithdrawn / abandoned Hubbard, MNMISO Sep 2022target 2027
Solar project J3217, Cottonwood County
Solar
60.0 MWWithdrawn / abandoned Cottonwood, MNMISO Sep 2022target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)