United States β€Ί Grid β€Ί Interconnection queues β€Ί Kansas

OCTARY USA Β· INTERCONNECTION QUEUES

Onshore wind interconnection queue in Kansas

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown317,545 MW
Active in queue7,545 MW31 requests
Agreement signed2,695 MW13 requests
Withdrawn24648.2 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

31 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GEN-2021-070, Hodgeman County
Onshore wind
504 MWIn study Hodgeman, KSSPP Apr 2021target 2027
Onshore wind project GEN-2024-102, Finney County
Onshore wind
401 MWIn study Finney, KSSPP Mar 2025target 2031
Onshore wind project GEN-2017-183, Hodgeman County
Onshore wind
400 MWAgreement signed Hodgeman, KSSPP Nov 2017target 2029
Onshore wind project GEN-2022-161, Butler County
Onshore wind
360 MWIn study Butler, KSSPP Feb 2023target 2029
Onshore wind project GEN-2016-111, Mcpherson County
Onshore wind
302 MWAgreement signed Mcpherson, KSSPP Nov 2016target 2027
Onshore wind project GEN-2024-258, Allen County
Onshore wind
300 MWIn study Allen, KSSPP Mar 2025target 2030
Onshore wind project GEN-2024-137, Scott County
Onshore wind
300 MWIn study Scott, KSSPP Mar 2025target 2030
Onshore wind project GEN-2024-138, Scott County
Onshore wind
300 MWIn study Scott, KSSPP Mar 2025target 2030
Onshore wind project GEN-2024-142, Mcpherson County
Onshore wind
300 MWIn study Mcpherson, KSSPP Mar 2025target 2031
Onshore wind project GEN-2021-056, Harper County
Onshore wind
300 MWAgreement signed Harper, KSSPP Apr 2021target 2030
Onshore wind project GEN-2024-016, Smith County
Onshore wind
300 MWIn study Smith, KSSPP Oct 2024target 2028
Onshore wind project GEN-2023-107, Finney County
Onshore wind
300 MWIn study Finney, KSSPP Oct 2023target 2030
Onshore wind project GEN-2024-144, Scott County
Onshore wind
300 MWIn study Scott, KSSPP Mar 2025target 2030
Onshore wind project GEN-2017-120, Dickinson County
Onshore wind
260 MWAgreement signed Dickinson, KSSPP Nov 2017target 2028
Onshore wind project GEN-2019-030, Ford County
Onshore wind
252 MWAgreement signed Ford, KSSPP Apr 2019target 2027
Onshore wind project GEN-2021-069, Hodgeman County
Onshore wind
250 MWIn study Hodgeman, KSSPP Apr 2021target 2027
Onshore wind project GEN-2024-193, Ford County
Onshore wind
250 MWIn study Ford, KSSPP Mar 2025target 2028
Onshore wind project GEN-2024-194, Ford County
Onshore wind
250 MWIn study Ford, KSSPP Mar 2025target 2028
Onshore wind project GEN-2021-068, Hodgeman County
Onshore wind
250 MWIn study Hodgeman, KSSPP Apr 2021target 2027
Onshore wind project GEN-2017-004, Cloud County
Onshore wind
202 MWAgreement signed Cloud, KSSPP Apr 2017target 2027
Onshore wind project GEN-2018-128, Sumner County
Onshore wind
200 MWAgreement signed Sumner, KSSPP Nov 2018target 2030
Onshore wind project GEN-2017-121, Sumner County
Onshore wind
200 MWAgreement signed Sumner, KSSPP Nov 2017target 2026
Onshore wind project GEN-2023-172, Kearny County
Onshore wind
200 MWIn study Kearny, KSSPP Oct 2023target 2029
Onshore wind project GEN-2017-119, Cloud County
Onshore wind
180 MWAgreement signed Cloud, KSSPP Nov 2017target 2027
Onshore wind project GEN-2017-086, Harper County
Onshore wind
150 MWAgreement signed Harper, KSSPP May 20172025
Onshore wind project GEN-2021-021, Stevens County
Onshore wind
150 MWIn study Stevens, KSSPP Apr 2021target 2027
Onshore wind project GEN-2018-009, Seward County
Onshore wind
150 MWAgreement signed Seward, KSSPP Apr 2018target 2029
Onshore wind project GEN-2023-173, Kearny County
Onshore wind
100 MWIn study Kearny, KSSPP Oct 2023target 2029
Onshore wind project GEN-2018-013, Dickinson County
Onshore wind
74.1 MWAgreement signed Dickinson, KSSPP Apr 2018target 2026
Onshore wind project GEN-2021-017, Cloud County
Onshore wind
37.5 MWIn study Cloud, KSSPP Apr 2021target 2027
Onshore wind project GEN-2019-001, Pratt County
Onshore wind
25.0 MWAgreement signed Pratt, KSSPP Nov 20182025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)