Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown385,997 MW
Active in queue5,997 MW38 requests
Agreement signed3,142 MW22 requests
Withdrawn8012.6 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

38 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Dolphin Solar
Solar Β· Dolphin Solar LLC
450 MWIn study Fountain, INPJM Sep 2020target 2024
Mammoth South Energy Center
Solar
300 MWAgreement signed Pulaski, INPJM Mar 2020target 2027
Mammoth Central Energy Center
Solar
300 MWAgreement signed Pulaski, INPJM Mar 2020target 2027
Mammoth Central II Energy Center
Solar
300 MWAgreement signed Pulaski, INPJM Sep 2020target 2028
Mayapple Solar
Solar
260 MWAgreement signed Pulaski, INPJM Sep 2020target 2027
Honey Creek Solar
Solar + storage
200 MWAgreement signed White, INPJM Feb 2020target 2027
Solar project J1616, Knox County
Solar
200 MWIn study Knox, INMISO Jun 2020target 2026
Solar project J1691, Sullivan County
Solar
200 MWIn study Sullivan, INMISO Jun 2020target 2026
Warren County Wind Energy Center
Onshore wind
200 MWAgreement signed INPJM Sep 2020target 2028
Solar project J1772, White County
Solar
200 MWIn study White, INMISO Jun 2020target 2026
Solar project J1780, Montgomery County
Solar
200 MWIn study Montgomery, INMISO Jun 2020target 2026
Moss Creek Solar
Solar
200 MWAgreement signed Pulaski, INPJM Mar 2020target 2027
Prairie Creek Wind
Onshore wind Β· Prairie Creek Wind, LLC
200 MWAgreement signed Blackford, INPJM Mar 2020target 2029
Teays River Wind Farm
Onshore wind Β· Teays River Wind Farm LLC f/k/a Blackford County Wind Farm LLC
200 MWIn study Blackford, INPJM Mar 2020target 2023
Solar project J1786, Sullivan County
Solar
200 MWIn study Sullivan, INMISO Jun 2020target 2026
Solar project J1721, Vigo County
Solar
175 MWIn study Vigo, INMISO Jun 2020target 2026
Solar project J1783, Montgomery County
Solar
150 MWIn study Montgomery, INMISO Jun 2020target 2025
Rosegold Solar
Solar Β· Leeward Renewable Energy Development, LLC
150 MWIn study Blackford, INPJM Jan 2020target 2022
Solar project J1782, Montgomery County
Solar
150 MWIn study Montgomery, INMISO Jun 2020target 2025
Solar project J1802, Marshall County
Solar
150 MWIn study Marshall, INMISO Jun 2020target 2024
Solar project J1646, Newton County
Solar
150 MWIn study Newton, INMISO Jun 2020target 2026
Magley Solar Energy Center
Solar
135 MWAgreement signed Adams, INPJM Sep 2020target 2029
Bluestem Solar
Solar Β· RWE Solar Development, LLC
125 MWIn study Laporte, INPJM Sep 2020target 2023
Bluestem Solar
Solar
125 MWAgreement signed Laporte, INPJM Mar 2020target 2027
Rainbow Trout
Solar + storage
120 MWAgreement signed Tippecanoe, INPJM Sep 2020target 2028
Flatrock Creek Solar II
Solar
100 MWAgreement signed Allen, INPJM Sep 2020target 2029
Prairie Creek Wind Phase 2
Onshore wind Β· Prairie Creek Wind Farm II, LLC
100 MWAgreement signed Blackford, INPJM Sep 2020target 2029
Flatrock Creek Solar I
Solar
100 MWAgreement signed Allen, INPJM Mar 2020target 2029
Tillman Solar Park
Solar
100 MWAgreement signed Allen, INPJM Sep 2020target 2029
Sun Chief Solar Farm
Solar
100 MWAgreement signed Jay, INPJM Jul 2020target 2027
Solar project J1736, Dubois County
Solar
100 MWIn study Dubois, INMISO Jun 2020target 2023
Fall Creek Energy Storage
Battery storage
80.0 MWAgreement signed Madison, INPJM Mar 2020target 2028
BR Solar Sheriff 1
Solar
75.0 MWAgreement signed Grant, INPJM Sep 2020target 2028
Bluestem Solar
Battery storage Β· RWE Solar Development, LLC
55.0 MWIn study Laporte, INPJM Sep 2020target 2023
Flatrock Creek Storage I
Battery storage
50.0 MWAgreement signed Allen, INPJM Sep 2020target 2029
Lake Trout Solar
Solar
45.0 MWAgreement signed Blackford, INPJM Mar 2020target 2028
New Jay PV & BESS
Solar + storage
39.0 MWAgreement signed Jay, INPJM Sep 2020target 2028
Bitter Ridge Wind Farm
Onshore wind
12.6 MWAgreement signed Jay, INPJM May 2020target 2025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)