United States β€Ί Grid β€Ί Interconnection queues β€Ί Illinois

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Illinois (2010 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown234,031 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn234,031 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

23 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project V4-074, Hancock County
Onshore wind
1,000 MWWithdrawn / abandoned Hancock, ILPJM Jan 2010target 2013
Onshore wind project W2-046, Livingston County
Onshore wind
450 MWWithdrawn / abandoned Livingston, ILPJM Jun 2010target 2013
Nuclear project W1-040, Lasalle County
Nuclear
350 MWWithdrawn / abandoned Lasalle, ILPJM Feb 2010target 2016
Onshore wind project W1-030, Ford County
Onshore wind
300 MWWithdrawn / abandoned Ford, ILPJM Feb 2010target 2014
Onshore wind project W1-031, Ford County
Onshore wind
300 MWWithdrawn / abandoned Ford, ILPJM Feb 2010target 2014
Onshore wind project G925, Dewitt County
Onshore wind
300 MWWithdrawn / abandoned Dewitt, ILMISO May 2010target 2010
Onshore wind project W3-046, Mason County
Onshore wind
208 MWWithdrawn / abandoned Mason, ILPJM Aug 2010target 2015
Onshore wind project W3-052, Woodford County
Onshore wind
200 MWWithdrawn / abandoned Woodford, ILPJM Aug 2010target 2012
Onshore wind project H003, Mcdonough County
Onshore wind
200 MWWithdrawn / abandoned Mcdonough, ILMISO Sep 2010target 2009
Onshore wind project J158, Piatt County
Onshore wind
150 MWWithdrawn / abandoned Piatt, ILMISO Aug 2010target 2012
Onshore wind project J159, Macon County
Onshore wind
101 MWWithdrawn / abandoned Macon, ILMISO Aug 2010target 2012
Onshore wind project J160, Macon County
Onshore wind
101 MWWithdrawn / abandoned Macon, ILMISO Aug 2010target 2012
Onshore wind project J128, Marshall County
Onshore wind
100 MWWithdrawn / abandoned Marshall, ILMISO Apr 2010target 2011
Onshore wind project J121, Ford County
Onshore wind
100 MWWithdrawn / abandoned Ford, ILMISO Apr 2010target 2012
Onshore wind project W4-019, Bureau County
Onshore wind
40.0 MWWithdrawn / abandoned Bureau, ILPJM Nov 2010target 2012
Solar project J169, Jersey County
Solar
20.0 MWWithdrawn / abandoned Jersey, ILMISO Sep 2010target 2015
Battery storage project W1-109, Cook County
Battery storage
20.0 MWWithdrawn / abandoned Cook, ILPJM Apr 2010target 2014
Onshore wind project W3-133, Stark County
Onshore wind
19.5 MWWithdrawn / abandoned Stark, ILPJM Oct 2010target 2011
Solar project W2-079, Winnebago County
Solar
19.4 MWWithdrawn / abandoned Winnebago, ILPJM Jul 2010target 2011
Solar project W3-132, Winnebago County
Solar
19.4 MWWithdrawn / abandoned Winnebago, ILPJM Oct 2010target 2011
Dresden Island Lock & Dam
Hydro
12.1 MWWithdrawn / abandoned Grundy, ILPJM Oct 2010target 2022
Brandon Road Lock & Dam
Hydro
10.6 MWWithdrawn / abandoned Will, ILPJM Oct 2010target 2022
Lincoln Solar
Solar
10.0 MWWithdrawn / abandoned Will, ILPJM Dec 2010target 2016

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)