United States โ€บ Grid โ€บ Interconnection queues โ€บ Georgia

OCTARY USA ยท INTERCONNECTION QUEUES

Interconnection queue in Georgia (2025 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown539,487 MW
Active in queue9,487 MW53 requests
Agreement signed0.0 MW0 requests
Withdrawn133,349 MW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

53 requests ยท page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Flint River 2 780 MW Unit
Gas
780 MWIn study Mitchell, GASoutheast Mar 2025target 2029
Gas project 25-IC-1330, Hancock County
Gas
759 MWIn study Hancock, GASoutheast Apr 2025target 2030
Gas project 25-IC-1329, Putnam County
Gas
759 MWIn study Putnam, GASoutheast Apr 2025target 2030
Gas project 25-IC-1327, Coweta County
Gas
759 MWIn study Coweta, GASoutheast Apr 2025target 2030
Battery storage project 25-IC-1374, Hancock County
Battery storage
600 MWIn study Hancock, GASoutheast Apr 2025target 2029
Battery storage project 25-IC-1311, Mcduffie County
Battery storage
500 MWIn study Mcduffie, GASoutheast Apr 2025target 2028
Battery storage project 25-IC-1385, Hancock County
Battery storage
450 MWIn study Hancock, GASoutheast Apr 2025target 2030
Battery storage project 25-IC-1375, Jackson County
Battery storage
325 MWIn study Jackson, GASoutheast Apr 2025target 2031
Battery storage project 25-IC-1312, Coweta County
Battery storage
250 MWIn study Coweta, GASoutheast Apr 2025target 2028
Battery storage project 25-IC-1313, Bartow County
Battery storage
250 MWIn study Bartow, GASoutheast Apr 2025target 2028
Solar project 25-IC-1326, Jasper County
Solar
250 MWIn study Jasper, GASoutheast Apr 2025target 2030
Battery storage project 25-IC-1334, Effingham County
Battery storage
250 MWIn study Effingham, GASoutheast Apr 2025target 2029
Solar + storage project 25-IC-1383, Dougherty County
Solar + storage
199 MWIn study Dougherty, GASoutheast Apr 2025target 2030
Solar project 25-IC-1342, Laurens County
Solar
199 MWIn study Laurens, GASoutheast Apr 2025target 2029
Battery storage project 25-IC-1314, Floyd County
Battery storage
193 MWIn study Floyd, GASoutheast Apr 2025target 2028
Solar project 25-IC-1340, Burke County
Solar
175 MWIn study Burke, GASoutheast Apr 2025target 2030
SR Dry Branch
Solar
172 MWIn study Twiggs, GASoutheast Jan 2025target 2029
Solar + storage project 25-IC-1339, Hancock County
Solar + storage
165 MWIn study Hancock, GASoutheast Apr 2025target 2029
Solar project 25-IC-1323, Dodge County
Solar
150 MWIn study Dodge, GASoutheast Apr 2025target 2028
Solar project 25-IC-1338, Marion County
Solar
150 MWIn study Marion, GASoutheast Apr 2025target 2029
Solar project 25-IC-1322, Taliaferro County
Solar
150 MWIn study Taliaferro, GASoutheast Apr 2025target 2028
SR Norwood III
Solar
150 MWIn study Warren, GASoutheast Jul 2025target 2029
Gas project 25-IC-1333B, Heard County
Gas
129 MWIn study Heard, GASoutheast Apr 2025target 2024
Gas project 25-IC-1333A, Heard County
Gas
129 MWIn study Heard, GASoutheast Apr 2025target 2030
Dougherty County BESS
Battery storage
120 MWIn study Dougherty, GASoutheast Mar 2025
Sawmill Junction
Solar
120 MWIn study Dodge, GASoutheast Mar 2025target 2029
Solar project 25-IC-1324, Dodge County
Solar
120 MWIn study Dodge, GASoutheast Apr 2025target 2029
Solar project 25-IC-1373, Pike County
Solar
120 MWIn study Pike, GASoutheast Apr 2025target 2028
Gas project 25-IC-1320B, Lee County
Gas
111 MWIn study Lee, GASoutheast Apr 2025target 2034
6505 US Hwy 221
Solar
110 MWIn study Jefferson, GASoutheast Apr 2025target 2028
Battery storage project 25-IC-1343, Laurens County
Battery storage
100 MWIn study Laurens, GASoutheast Apr 2025target 2028
Solar + storage project 25-IC-1387, Sumter County
Solar + storage
92.0 MWIn study Sumter, GASoutheast Apr 2025target 2028
Solar + storage project 25-IC-1384, Tift County
Solar + storage
88.0 MWIn study Tift, GASoutheast Apr 2025target 2029
Solar project 25-IC-1372, Elbert County
Solar
79.0 MWIn study Elbert, GASoutheast Apr 2025target 2030
Nuclear project 25-IC-1302, Appling County
Nuclear
65.0 MWIn study Appling, GASoutheast Mar 2025target 2031
SR Millen
Solar
65.0 MWIn study Jenkins, GASoutheast Jan 2025target 2029
Nuclear project 25-IC-1301, Appling County
Nuclear
60.0 MWIn study Appling, GASoutheast Mar 2025target 2030
Nuclear project 25-IC-1300, Burke County
Nuclear
50.0 MWIn study Burke, GASoutheast Mar 2025target 2031
Nuclear project 25-IC-1298, Burke County
Nuclear
50.0 MWIn study Burke, GASoutheast Mar 2025target 2030
Gas project 25-IC-1286, Effingham County
Gas
35.0 MWIn study Effingham, GASoutheast Mar 2025target 2028
Gas project 25-IC-1285, Effingham County
Gas
35.0 MWIn study Effingham, GASoutheast Mar 2025target 2028
Nuclear project 25-IC-1303, Burke County
Nuclear
20.0 MWIn study Burke, GASoutheast Mar 2025target 2027
Nuclear project 25-IC-1304, Burke County
Nuclear
16.0 MWIn study Burke, GASoutheast Mar 2025target 2027
Nuclear project 25-IC-1297, Burke County
Nuclear
15.0 MWIn study Burke, GASoutheast Mar 2025target 2029
Nuclear project 25-IC-1299, Burke County
Nuclear
15.0 MWIn study Burke, GASoutheast Mar 2025target 2028
Gas project 25-IC-1289, Effingham County
Gas
13.5 MWIn study Effingham, GASoutheast Mar 2025target 2028
Gas project 25-IC-1287, Effingham County
Gas
13.5 MWIn study Effingham, GASoutheast Mar 2025target 2027
Gas project 25-IC-1288, Effingham County
Gas
13.5 MWIn study Effingham, GASoutheast Mar 2025target 2028
Gas project 25-IC-1290, Effingham County
Gas
13.5 MWIn study Effingham, GASoutheast Mar 2025target 2029
Gas project 25-IC-1292, Effingham County
Gas
13.5 MWIn study Effingham, GASoutheast Mar 2025target 2031
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)