🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Georgia

SOLAR · SOUTHEAST

Solar project 25-IC-1340, Burke County

Solar project 25-IC-1340, Burke County is a 175 MW solar request in interconnection study in the Southeast interconnection queue, in Burke County, Georgia, connecting to Southern Company.

Queue statusIn planning
  1. PlanningQueued Apr 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget May 2030 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
25-IC-1340
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Waynesboro Primary - Wilson 230 kV Line
Location
Burke County, Georgia
Technology
Solar: 175 MW
Total requested
175 MW
Service type
Energy only (ERIS)
Study phase
Facility Study
Queue status
Active
Entered queue
14 April 2025
Proposed online date
May 2030

Location

Marker shows the centre of Burke County; the queue data does not give exact sites.

Power plants in Georgia · Transmission lines in Georgia

Other requests in Burke County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem