United States › Grid › Interconnection queues › Georgia
NUCLEAR · SOUTHEASTVogtle Unit 3
Vogtle Unit 3 is a 1,158 MW nuclear request built and operating in the Southeast interconnection queue, in Burke County, Georgia, connecting to Southern Company.
Request details
- Queue ID
- IC-236
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Southern Company
- Location
- Burke County, Georgia
- Technology
- Nuclear: 1,158 MW
- Total requested
- 1,158 MW
- Study phase
- Operational
- Queue status
- Operational
- Entered queue
- 25 March 2010
- Agreement signed
- 28 October 2013
- Proposed online date
- December 2014
- Came online
- April 2024
Location
Marker shows the centre of Burke County; the queue data does not give exact sites.
Other requests in Burke County
- Solar project IC-759, Burke CountySolar · 40.0 MW · agreement signed
- Solar project 25-IC-1340, Burke CountySolar · 175 MW · in study
- TOCE GA 1 SolarSolar · 125 MW · in study
- Nuclear project 25-IC-1300, Burke CountyNuclear · 50.0 MW · in study
- Nuclear project 25-IC-1298, Burke CountyNuclear · 50.0 MW · in study
- Nuclear project 25-IC-1303, Burke CountyNuclear · 20.0 MW · in study
- Nuclear project 25-IC-1304, Burke CountyNuclear · 16.0 MW · in study
- Nuclear project 25-IC-1297, Burke CountyNuclear · 15.0 MW · in study
- Nuclear project 25-IC-1299, Burke CountyNuclear · 15.0 MW · in study
- Solar project IC-1005, Burke CountySolar · 100 MW · suspended
- Vogtle Unit 4Nuclear · 1,158 MW · built
- White Oak SolarSolar · 76.5 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem