United States βΊ Grid βΊ Interconnection queues
NUCLEAR Β· SOUTHEASTVogtle Unit 4
Vogtle Unit 4 is a 1,158 MW nuclear request built and operating in the Southeast interconnection queue, connecting to Southern Company.
Request details
- Queue ID
- IC-237
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Southern Company
- Technology
- Nuclear: 1,158 MW
- Total requested
- 1,158 MW
- Study phase
- Operational
- Queue status
- Operational
- Entered queue
- 25 March 2010
- Proposed online date
- December 2014
- Came online
- April 2024
Location
Marker shows the centre of County; the queue data does not give exact sites.
Other requests in County
- Solar project IC-759, Burke CountySolar Β· 40.0 MW Β· agreement signed
- Solar project 25-IC-1340, Burke CountySolar Β· 175 MW Β· in study
- TOCE GA 1 SolarSolar Β· 125 MW Β· in study
- Nuclear project 25-IC-1300, Burke CountyNuclear Β· 50.0 MW Β· in study
- Nuclear project 25-IC-1298, Burke CountyNuclear Β· 50.0 MW Β· in study
- Nuclear project 25-IC-1303, Burke CountyNuclear Β· 20.0 MW Β· in study
- Nuclear project 25-IC-1304, Burke CountyNuclear Β· 16.0 MW Β· in study
- Nuclear project 25-IC-1297, Burke CountyNuclear Β· 15.0 MW Β· in study
- Nuclear project 25-IC-1299, Burke CountyNuclear Β· 15.0 MW Β· in study
- Solar project IC-1005, Burke CountySolar Β· 100 MW Β· suspended
- Vogtle Unit 3Nuclear Β· 1,158 MW Β· built
- White Oak SolarSolar Β· 76.5 MW Β· built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem