United States βΊ Grid βΊ Interconnection queues βΊ Georgia
OCTARY USA Β· INTERCONNECTION QUEUESQueue requests in study in Georgia (2024 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Smarr CC Gas |
2,000 MW | In study |
| Flint River 780 MW Unit Gas |
780 MW | In study |
| Gas project IC-1260, Effingham County Gas |
722 MW | In study |
| TOCE GA Solar 4 Solar + storage |
325 MW | In study |
| Talbot U7 Gas |
250 MW | In study |
| Washington County Solar Solar + storage |
203 MW | In study |
| Battery storage project IC-1272, Paulding County Battery storage |
200 MW | In study |
| SR Bartown frmly Jefferson Solar |
200 MW | In study |
| SR Wrens Solar |
194 MW | In study |
| SR Norwood II Solar |
143 MW | In study |
| Spain Energy Center Solar + storage |
141 MW | In study |
| SR Warthen Solar |
135 MW | In study |
| SR Doerun Solar |
130 MW | In study |
| Rebecca Solar Solar |
120 MW | In study |
| Scarboro Solar Solar + storage |
75.0 MW | In study |
| Altamaha Green Energy Other |
70.0 MW | In study |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)