United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Southeast (non-ISO utilities) (2017 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown282,517 MW
Active in queue2,517 MW28 requests
Agreement signed1,519 MW15 requests
Withdrawn20816.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

28 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project IC-652, Sumter County
Solar
615 MWAgreement signed Sumter, GASoutheast Sep 2017target 2023
Onshore wind project GI-61, Nodaway County
Onshore wind
230 MWAgreement signed Nodaway, MOSoutheast May 2017target 2019
Oakhurst Solar Farm
Solar + storage
200 MWIn study Mitchell, GASoutheast Apr 20172021
Solar project IC-616, Pierce County
Solar
118 MWAgreement signed Pierce, GASoutheast Mar 2017target 2020
Solar project 313, Monroe County
Solar
100 MWAgreement signed Monroe, MSSoutheast May 2017target 2026
Solar project LGE-GIS-2017-002, Lyon County
Solar
86.0 MWAgreement signed Lyon, KYSoutheast Mar 2017target 2024
Solar project 948720, Nash County
Solar Β· Duke Energy Progress, LLC
80.0 MWUnder construction Nash, NCSoutheast Jun 2017target 2025
Solar project 202.1, Levy County
Solar Β· FL SB 9, LLC
74.9 MWUnder construction Levy, FLSoutheast Oct 2017target 2021
Solar project 276, Union County
Solar Β· FPL
74.5 MWIn study Union, FLSoutheast Jun 2017target 2029
Solar project 20
Solar
74.5 MWPaused / redesign FLSoutheast Oct 2017target 2019
Solar project 306, Brevard County
Solar Β· FPL
74.5 MWIn study Brevard, FLSoutheast Jun 2017target 2026
Solar project 280, Hendry County
Solar Β· FPL
74.5 MWIn study Hendry, FLSoutheast Jun 2017target 2027
Solar project 289, Miami-Dade County
Solar Β· FPL
74.5 MWIn study Miami-Dade, FLSoutheast Jun 2017target 2028
Solar + storage project 333, Shelby County
Solar + storage
74.0 MWAgreement signed Shelby, TNSoutheast Oct 2017target 2024
Solar project 193, Levy County
Solar Β· Origis Development LLC
70.0 MWIn study Levy, FLSoutheast Aug 2017target 2021
Solar project 48968, Chester County
Solar
69.8 MWAgreement signed Chester, SCSoutheast Nov 2017target 2027
Solar project 314, Monroe County
Solar
60.0 MWAgreement signed Monroe, MSSoutheast May 2017target 2021
Solar project JEA-Q007-PV, Duval County
Solar
50.0 MWAgreement signed Duval, FLSoutheast Dec 2017target 2026
Solar project JEA-Q005-PV, Duval County
Solar
50.0 MWPaused / redesign Duval, FLSoutheast Dec 2017target 2035
Solar project JEA-Q006-PV, Duval County
Solar
50.0 MWPaused / redesign Duval, FLSoutheast Dec 2017target 2050
Solar project JEA-Q004-PV, Duval County
Solar
50.0 MWPaused / redesign Duval, FLSoutheast Dec 2017target 2050
Solar project JEA-Q003-PV, Duval County
Solar
50.0 MWPaused / redesign Duval, FLSoutheast Dec 2017target 2050
Hydro project 323, Marion County
Hydro
27.0 MWAgreement signed Marion, TNSoutheast Aug 2017target 2022
Hydro project 322, Marion County
Hydro
27.0 MWAgreement signed Marion, TNSoutheast Aug 2017target 2021
Gas project 332, Shelby County
Gas
23.0 MWAgreement signed Shelby, TNSoutheast Oct 2017target 2018
Onshore wind project GI-60, Gentry County
Onshore wind
18.0 MWAgreement signed Gentry, MOSoutheast Apr 2017
Hydro project 320, Marion County
Hydro
11.0 MWAgreement signed Marion, TNSoutheast Aug 2017target 2019
Hydro project 321, Marion County
Hydro
11.0 MWAgreement signed Marion, TNSoutheast Aug 2017target 2021

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)