United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Completed queue projects in Southeast (non-ISO utilities) (2020 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown372,675 MW
Active in queue7,020 MW55 requests
Agreement signed4,069 MW24 requests
Withdrawn17830.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

37 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Wadley Solar
Other
260 MWOperating Jefferson, GASoutheast Jul 20202024
SR Toombs
Solar
250 MWOperating Toombs, GASoutheast Apr 2020target 2024
Solar project 415, Lowndes County
Solar
100 MWOperating Lowndes, MSSoutheast Feb 2020target 2023
Gas project 418, Miami-Dade County
Gas Β· FPL
99.0 MWOperating Miami-Dade, FLSoutheast Sep 20202025
CPV Stagecoach Solar
Solar
80.0 MWOperating Macon, GASoutheast Jul 20202024
Solar project 72, Polk County
Solar
74.9 MWOperating Polk, FLSoutheast Aug 2020target 2023
Solar project 281, Bay County
Solar Β· Duke Energy Florida, LLC
74.9 MWOperating Bay, FLSoutheast Apr 20202023
Solar project 277, Alachua County
Solar Β· Origis Holdings USA Subco, LLC
74.9 MWOperating Alachua, FLSoutheast Mar 20202022
Solar project 288, Madison County
Solar Β· Duke Energy Florida, LLC
74.9 MWOperating Madison, FLSoutheast Oct 20202024
Solar project 282, Bay County
Solar Β· Duke Energy Florida, LLC
74.9 MWOperating Bay, FLSoutheast Apr 20202022
Solar project 285, Gulf County
Solar Β· Duke Energy Florida, LLC
74.9 MWOperating Gulf, FLSoutheast Apr 20202024
Solar project 71, Pasco County
Solar
74.9 MWOperating Pasco, FLSoutheast Aug 2020target 2023
Solar project 378B, Jackson County
Solar Β· FPL
74.5 MWOperating Jackson, FLSoutheast Feb 20202023
Solar project 399, St. Lucie County
Solar Β· FPL
74.5 MWOperating St. Lucie, FLSoutheast Jul 20202024
Solar project 403, St. Lucie County
Solar Β· FPL
74.5 MWOperating St. Lucie, FLSoutheast Jul 20202025
Solar project 402, St. Lucie County
Solar Β· FPL
74.5 MWOperating St. Lucie, FLSoutheast Jul 20202024
Solar project 378G, Walton County
Solar Β· FPL
74.5 MWOperating Walton, FLSoutheast Feb 20202024
Solar project 380B, Escambia County
Solar Β· FPL
74.5 MWOperating Escambia, FLSoutheast Feb 20202024
Solar project 409, Desoto County
Solar Β· FPL
74.5 MWOperating Desoto, FLSoutheast Jul 20202025
Solar project 401, St. Lucie County
Solar Β· FPL
74.5 MWOperating St. Lucie, FLSoutheast Jul 20202024
Solar project 380A, Walton County
Solar Β· FPL
74.5 MWOperating Walton, FLSoutheast Feb 20202025
Solar project 378D, Escambia County
Solar Β· FPL
74.5 MWOperating Escambia, FLSoutheast Feb 20202024
Solar project 66, Hillsborough County
Solar
74.5 MWOperating Hillsborough, FLSoutheast Jan 2020target 2021
Solar project 400, Okeechobee County
Solar Β· FPL
74.5 MWOperating Okeechobee, FLSoutheast Jul 20202025
Solar project 381, Desoto County
Solar Β· FPL
74.5 MWOperating Desoto, FLSoutheast Apr 20202024
Solar project 380C, Washington County
Solar Β· FPL
74.5 MWOperating Washington, FLSoutheast Feb 20202023
GPC Mossy Branch Battery Storage Station
Battery storage
65.0 MWOperating Talbot, GASoutheast Apr 20202024
Gas project 116552
Gas Β· Broad River Energy LLC
50.0 MWOperating Southeast May 2020
Gas project 416, Lee County
Gas Β· FPL
42.0 MWOperating Lee, FLSoutheast Sep 20202024
Battery storage project 380, Suwannee County
Battery storage Β· FPL
30.0 MWOperating Suwannee, FLSoutheast Feb 20202021
Battery storage project 379, Columbia County
Battery storage Β· FPL
30.0 MWOperating Columbia, FLSoutheast Feb 20202021
Gas project 64646, Richmond County
Gas Β· Duke Energy Progress, LLC
22.0 MWOperating Richmond, NCSoutheast Jan 20202022
Gas project 64750, Richmond County
Gas Β· Duke Energy Progress, LLC
21.0 MWOperating Richmond, NCSoutheast Jan 20202023
Gas project 64758, Richmond County
Gas Β· Duke Energy Progress, LLC
20.0 MWOperating Richmond, NCSoutheast Jan 20202023
Gas project 64734, Richmond County
Gas Β· Duke Energy Progress, LLC
20.0 MWOperating Richmond, NCSoutheast Jan 20202023
Gas project 63790, Richmond County
Gas Β· Duke Energy Progress, LLC
18.0 MWOperating Richmond, NCSoutheast Jan 20202022
Solar project 75, Hillsborough County
Solar
1.0 MWOperating Hillsborough, FLSoutheast Sep 2020target 2020

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)