Solar project 288, Madison County

Solar project 288, Madison County is a 74.9 MW solar request built and operating in the Southeast interconnection queue, in Madison County, Florida, connecting to Duke Energy Florida.

Queue statusOperating
  1. PlanningQueued Oct 2020 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingMar 2024 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
288
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Duke Energy Florida
Developer
Duke Energy Florida, LLC
Connection point (POI)
Birch Switching Station
Location
Madison County, Florida
Technology
Solar: 74.9 MW
Total requested
74.9 MW
Service type
Network resource (NRIS)
Study phase
IA Executed
Queue status
Operational
Entered queue
7 October 2020
Proposed online date
March 2024
Came online
March 2024

Location

Marker shows the centre of Madison County; the queue data does not give exact sites.

Power plants in Florida · Transmission lines in Florida

Other requests in Madison County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem