🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Florida

SOLAR · SOUTHEAST

Solar project 306, Madison County

Solar project 306, Madison County is a 74.9 MW solar request built and operating in the Southeast interconnection queue, in Madison County, Florida, connecting to Duke Energy Florida.

Queue statusOperating
  1. PlanningQueued Apr 2022 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingJul 2025 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
306
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Duke Energy Florida
Developer
Duke Energy Florida, LLC
Connection point (POI)
Birch Switching Station
Location
Madison County, Florida
Technology
Solar: 74.9 MW
Total requested
74.9 MW
Service type
Network resource (NRIS)
Study phase
IA Executed
Queue status
Operational
Entered queue
8 April 2022
Proposed online date
June 2024
Came online
July 2025

Location

Marker shows the centre of Madison County; the queue data does not give exact sites.

Power plants in Florida · Transmission lines in Florida

Other requests in Madison County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem