Solar project 380A, Walton County

Solar project 380A, Walton County is a 74.5 MW solar request built and operating in the Southeast interconnection queue, in Walton County, Florida, connecting to Florida Power & Light.

Queue statusOperating
  1. PlanningQueued Feb 2020 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingJan 2025 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
380A
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Florida Power & Light
Developer
FPL
Connection point (POI)
Shoal River - Samson (APC) 230 kV line
Location
Walton County, Florida
Technology
Solar: 74.5 MW
Total requested
74.5 MW
Service type
Network resource (NRIS)
Study phase
IA Executed
Queue status
Operational
Entered queue
6 February 2020
Proposed online date
January 2025
Came online
January 2025

Location

Marker shows the centre of Walton County; the queue data does not give exact sites.

Power plants in Florida · Transmission lines in Florida

Other requests in Walton County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem