CPV Stagecoach Solar

CPV Stagecoach Solar is a 80.0 MW solar request built and operating in the Southeast interconnection queue, in Macon County, Georgia, connecting to Southern Company.

Queue statusOperating
  1. PlanningQueued Jul 2020 (completed)
  2. ConsentedNov 2021 (completed)
  3. Construction (completed)
  4. OperatingMay 2024 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
IC-882
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Location
Macon County, Georgia
Technology
Solar: 80.0 MW
Total requested
80.0 MW
Study phase
Operational
Queue status
Operational
Entered queue
13 July 2020
Agreement signed
29 November 2021
Proposed online date
June 2023
Came online
May 2024

Location

Marker shows the centre of Macon County; the queue data does not give exact sites.

Power plants in Georgia · Transmission lines in Georgia

Other requests in Macon County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem