Interconnection queue in North Dakota, SPP

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown266,843 MW
Active in queue6,843 MW26 requests
Agreement signed1,127 MW7 requests
Withdrawn5310.7 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

26 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project ERAS-2025-012, Mercer County
Gas
750 MWIn study Mercer, NDSPP Oct 2025target 2030
Gas project ERAS-2025-011, Mercer County
Gas
750 MWIn study Mercer, NDSPP Oct 2025target 2030
Gas project GEN-2024-082, Williams County
Gas
745 MWIn study Williams, NDSPP Oct 2024target 2030
Gas project GEN-2024-081, Williams County
Gas
745 MWIn study Williams, NDSPP Oct 2024target 2029
Onshore wind project GEN-2024-141, Mercer County
Onshore wind
424 MWIn study Mercer, NDSPP Mar 2025target 2031
Battery storage project GEN-2024-331, Dunn County
Battery storage
300 MWIn study Dunn, NDSPP Mar 2025target 2028
Onshore wind project GEN-2018-067, Williams County
Onshore wind
255 MWAgreement signed Williams, NDSPP Oct 2018target 2028
Other project GEN-2022-010, Williams County
Other
250 MWIn study Williams, NDSPP May 20222025
Gas project GEN-2022-083, Williams County
Gas
250 MWIn study Williams, NDSPP Oct 20222025
Battery storage project GEN-2024-328, Slope County
Battery storage
250 MWIn study Slope, NDSPP Mar 2025target 2028
Battery storage project GEN-2024-326, Stark County
Battery storage
225 MWIn study Stark, NDSPP Mar 2025target 2028
Onshore wind project GEN-2016-004, Oliver County
Onshore wind
202 MWAgreement signed Oliver, NDSPP Mar 2016target 2027
Battery storage project GEN-2024-329, Williams County
Battery storage
200 MWIn study Williams, NDSPP Mar 2025target 2028
Battery storage project GEN-2024-327, Ward County
Battery storage
200 MWIn study Ward, NDSPP Mar 2025target 2028
Solar project GEN-2024-284, Mercer County
Solar
199 MWIn study Mercer, NDSPP Mar 2025target 2028
Battery storage project GEN-2024-034, Sargent County
Battery storage
175 MWIn study Sargent, NDSPP Oct 2024target 2029
Battery storage project GEN-2023-SR4, Burke County
Battery storage
170 MWAgreement signed Burke, NDSPP Dec 2022target 2026
Solar project GEN-2019-037, Mercer County
Solar
150 MWAgreement signed Mercer, NDSPP May 2019target 2023
Solar project GEN-2020-091, Mckenzie County
Solar
150 MWAgreement signed Mckenzie, NDSPP Apr 2020target 2029
Other project GEN-2022-009, Williams County
Other
125 MWIn study Williams, NDSPP May 20222025
Battery storage project GEN-2024-359, Stark County
Battery storage
100 MWIn study Stark, NDSPP Mar 2025target 2030
Onshore wind project GEN-2017-215, Ward County
Onshore wind
100 MWAgreement signed Ward, NDSPP Nov 2017target 2030
Onshore wind project GEN-2017-214, Ward County
Onshore wind
100 MWAgreement signed Ward, NDSPP Nov 2017target 2030
Battery storage project GEN-2024-SR12, Lamoure County
Battery storage
20.0 MWIn study Lamoure, NDSPP May 2024target 2026
Onshore wind project GEN-2025-GR5, Ward County
Onshore wind
7.7 MWIn study Ward, NDSPP Oct 2025
Onshore wind project GEN-2025-GR3, Mclean County
Onshore wind
0.0 MWIn study Mclean, NDSPP Oct 2025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)