🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › North Dakota

GAS · SPP

Gas project GEN-2022-083, Williams County

Gas project GEN-2022-083, Williams County is a 250 MW gas request in interconnection study in the SPP interconnection queue, in Williams County, North Dakota, connecting to BEPC.

Queue statusIn planning
  1. PlanningQueued Oct 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingJun 2025 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GEN-2022-083
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
BEPC
Connection point (POI)
Judson Substation 345 kV
Location
Williams County, North Dakota
Technology
Gas: 250 MW
Total requested
250 MW
Service type
Energy only (ERIS)
Study phase
FACILITY STUDY STAGE
Queue status
Active
Entered queue
21 October 2022
Proposed online date
June 2025
Came online
June 2025

Location

Marker shows the centre of Williams County; the queue data does not give exact sites.

Power plants in North Dakota · Transmission lines in North Dakota

Other requests in Williams County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem