Gas project GI-1406, Williams County

Gas project GI-1406, Williams County is a 125 MW gas request built and operating in the West interconnection queue, in Williams County, North Dakota, connecting to WAPA/BEPC/HCPD Integrated System.

Queue statusOperating
  1. PlanningQueued Jun 2014 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingTarget May 2016 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
GI-1406
Grid region
West (non-ISO utilities)
Utility / transmission owner
WAPA/BEPC/HCPD Integrated System
Developer
Basin Electric
Connection point (POI)
Williston 115kV
Location
Williams County, North Dakota
Technology
Gas: 125 MW
Total requested
125 MW
Service type
NRIS and ERIS
Study phase
IAE/IS
Queue status
Operational
Entered queue
9 June 2014
Proposed online date
May 2016

Location

Marker shows the centre of Williams County; the queue data does not give exact sites.