United States โบ Grid โบ Interconnection queues โบ Indiana
OCTARY USA ยท INTERCONNECTION QUEUESQueue requests in study in Indiana, PJM
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Gas project AG2-072, Spencer County Gas ยท Bluegrass Power LLC |
700 MW | In study |
| Solar project AH2-348, Daviess County Solar |
700 MW | In study |
| Dolphin Solar Solar ยท Dolphin Solar LLC |
450 MW | In study |
| Battery storage project AI1-022, Huntington County Battery storage |
450 MW | In study |
| Solar project AH2-352 Solar |
400 MW | In study |
| Solar project AH2-257, Vermillion County Solar |
400 MW | In study |
| Solar + storage project AH2-413, Huntington County Solar + storage |
365 MW | In study |
| Battery storage project AH2-414, Huntington County Battery storage |
350 MW | In study |
| Solar project AI1-085, Wayne County Solar |
290 MW | In study |
| Vermilion Grove Wind Onshore wind ยท Vermilion Grove Wind, LLC |
255 MW | In study |
| Solar + storage project AH2-112, St. Joseph County Solar + storage |
250 MW | In study |
| Solar project AG2-029, Noble County Solar ยท Southern Pike Solar LLC |
250 MW | In study |
| Solar project AG2-163, Fountain County Solar ยท Dolphin Solar LLC |
250 MW | In study |
| Solar project AG2-245, Starke County Solar ยท STARKE CENTRAL PROJECT, LLC |
210 MW | In study |
| Solar + storage project AH2-419, Laporte County Solar + storage |
210 MW | In study |
| Solar + storage project AH2-025, Fountain County Solar + storage |
200 MW | In study |
| Solar + storage project AI1-134, Grant County Solar + storage |
200 MW | In study |
| Teays River Wind Farm Onshore wind ยท Teays River Wind Farm LLC f/k/a Blackford County Wind Farm LLC |
200 MW | In study |
| Battery storage project AH2-347, St. Joseph County Battery storage |
200 MW | In study |
| Solar + storage project AH2-153, Vermillion County Solar + storage |
180 MW | In study |
| Onshore wind project AI1-003, Huntington County Onshore wind |
170 MW | In study |
| Golden Aster Solar Energy Center Solar |
160 MW | Paused / redesign |
| Solar project AG2-230, St. Joseph County Solar ยท Dumont Solar, LLC |
150 MW | In study |
| Bowfin Solar Solar + storage |
150 MW | Paused / redesign |
| Solar + storage project AH2-154, Vermillion County Solar + storage |
150 MW | In study |
| Solar project AG2-637, Randolph County Solar ยท ACE Development Company, LLC |
150 MW | In study |
| Rosegold Solar Solar ยท Leeward Renewable Energy Development, LLC |
150 MW | In study |
| Solar + storage project AG2-126, Vermillion County Solar + storage ยท TGE Illinois 211, LLC |
150 MW | In study |
| Meadow Forge Solar Energy Center Solar |
130 MW | Paused / redesign |
| Solar + storage project AI1-080, Laporte County Solar + storage |
125 MW | In study |
| Bluestem Solar Solar ยท RWE Solar Development, LLC |
125 MW | In study |
| Solar project AG2-491, White County Solar ยท Black Prairie Solar Park II LLC |
100 MW | In study |
| Battery storage project AG2-332, Elkhart County Battery storage ยท Amberjack Solar LLC |
100 MW | In study |
| Headwaters Wind Farm III Onshore wind |
100 MW | Paused / redesign |
| Madison County Solar Solar |
100 MW | Paused / redesign |
| Battery storage project AG2-343, Fountain County Battery storage ยท Dolphin Solar LLC |
100 MW | In study |
| Solar project AG2-550, Randolph County Solar ยท Riverstart Solar Park VI LLC |
100 MW | In study |
| Headwaters Wind Farm III Onshore wind |
100 MW | Paused / redesign |
| Solar + storage project AI1-081, Jay County Solar + storage |
100 MW | In study |
| Battery storage project AH2-233, Pulaski County Battery storage |
100 MW | In study |
| Riverstart Solar Park V Solar |
100 MW | Paused / redesign |
| Battery storage project AG2-248, Elkhart County Battery storage ยท Amberjack Solar LLC |
100 MW | In study |
| Solar + storage project AI1-009, Rush County Solar + storage |
100 MW | In study |
| Solar project AH1-392, St. Joseph County Solar ยท ibV Energy Partners LLC |
90.0 MW | In study |
| Solar project AI2-115, Delaware County Solar |
84.0 MW | In study |
| Battery storage project AH1-482, Pulaski County Battery storage ยท Lightsource Renewable Energy Development, LLC |
78.0 MW | In study |
| Battery storage project AH2-227, Jay County Battery storage |
75.0 MW | In study |
| Battery storage project AH1-302, Pulaski County Battery storage ยท Bottlebrush Solar Energy LLC |
75.0 MW | In study |
| Solar + storage project AG2-519, Delaware County Solar + storage ยท Muncie Solar 1, LLC |
66.5 MW | In study |
| Dover Solar Facility Solar |
55.0 MW | Paused / redesign |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- MISO (Midcontinent)137 ยท 34.7 GW
- PJM (Mid-Atlantic, Midwest)78 ยท 10.9 GW
- Southeast (non-ISO utilities)1 ยท 500 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)