United States β€Ί Grid β€Ί Interconnection queues β€Ί Indiana

OCTARY USA Β· INTERCONNECTION QUEUES

Completed queue projects in Indiana, PJM

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown344,370 MW
Active in queue17.4 GW117 requests
Agreement signed6,500 MW39 requests
Withdrawn21040.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

34 requests
ProjectCapacityStatusLocationRegionQueuedOnline
St. Joseph Energy Center, LLC
Gas
675 MWOperating St. Joseph, INPJM Jun 20112018
Fowler Ridge WF
Onshore wind
500 MWOperating Benton, INPJM Feb 20062008
Mammoth North Solar Project
Solar
300 MWOperating Starke, INPJM Sep 20192024
Fowler Ridge 4 WF
Onshore wind
250 MWOperating Benton, INPJM Feb 20062015
Meadow Lake
Onshore wind
202 MWOperating White, INPJM Feb 20072009
Wildcat Wind Farm I
Onshore wind
200 MWOperating Madison, INPJM Aug 20082012
Meadow Lake WF 4 - 5
Onshore wind
200 MWOperating White, INPJM Jan 20082010
Meadow Lake WF II, Meadow Lake WF III
Onshore wind
200 MWOperating Benton, INPJM Jan 20082010
Meadow Lake Wind Farm VI
Onshore wind
200 MWOperating White, INPJM May 20152018
HeadwatersWF
Onshore wind
200 MWOperating Randolph, INPJM Jul 20082014
Headwaters II
Onshore wind
200 MWOperating Randolph, INPJM Aug 20092021
Bellflower Solar 1
Solar
153 MWOperating Henry, INPJM Mar 20192022
Honeysuckle Solar Project
Solar
150 MWOperating St. Joseph, INPJM Sep 20192025
Bitter Ridge Wind Farm
Onshore wind
130 MWOperating Jay, INPJM Mar 20172020
Bluff Point
Onshore wind
120 MWOperating Jay, INPJM Jul 20072017
Riverstart Solar Park
Solar
100 MWOperating Randolph, INPJM Oct 20162021
Mammoth North Solar Project
Solar
100 MWOperating Starke, INPJM Mar 20202024
Riverstart Solar Park III
Solar
100 MWOperating Randolph, INPJM Mar 20172024
Riverstart Solar Park
Solar
100 MWOperating Randolph, INPJM Oct 20162021
Lawrenceburg Generating Plant
Gas
50.0 MWOperating Dearborn, INPJM Oct 20162019
Lawrenceburg Generating Plant
Gas
50.0 MWOperating Dearborn, INPJM Oct 20162019
St. Joseph's Energy Center, LLC
Gas
40.0 MWOperating St. Joseph, INPJM Sep 20152018
Rockport Unit #1
Coal
36.0 MWOperating Spencer, INPJM Feb 20132017
Montpelier
Gas
27.0 MWOperating Wells, INPJM Feb 20062008
St. Joseph County, Indiana
Solar
20.0 MWOperating St. Joseph, INPJM Mar 20182021
Rockport Unit 1
Coal
20.0 MWOperating Spencer, INPJM Jan 20072011
Montpelier
Gas
19.0 MWOperating Wells, INPJM Mar 20072008
Tanners Creek #2
Coal
5.0 MWOperating Dearborn, INPJM Jan 20072007
Tanners Creek #1
Coal
5.0 MWOperating Dearborn, INPJM Jan 20072007
Olive Solar Facility
Solar
5.0 MWOperating St. Joseph, INPJM Apr 20142016
Wabash Valley Power Association, Inc.
Other
4.8 MWOperating Elkhart, INPJM Jan 20132015
Wabash Valley Power Association, Inc.
Other
3.2 MWOperating Jay, INPJM Jan 20132015
Twin Branch Solar Facility
Solar
2.6 MWOperating St. Joseph, INPJM Apr 20142016
Deer Creek Solar Facility
Solar
2.5 MWOperating Grant, INPJM Apr 20142016

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)