United States βΊ Grid βΊ Interconnection queues βΊ Indiana
GAS Β· PJMMontpelier
Montpelier is a 27.0 MW gas request built and operating in the PJM interconnection queue, in Wells County, Indiana, connecting to AEP.
Request details
- Queue ID
- Q10
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Keystone 345kV
- Location
- Wells County, Indiana
- Technology
- Gas: 27.0 MW
- Total requested
- 27.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
- Queue status
- Operational
- Entered queue
- 23 February 2006
- Proposed online date
- December 2008
- Came online
- December 2008
Location
Marker shows the centre of Wells County; the queue data does not give exact sites.
Other requests in Wells County
- MontpelierGas Β· 19.0 MW Β· built
- Paddlefish SolarSolar + storage Β· 350 MW Β· withdrawn
- Wells County Wind FarmOnshore wind Β· 300 MW Β· withdrawn
- Onshore wind project V4-021, Wells CountyOnshore wind Β· 300 MW Β· withdrawn
- Solar + storage project AF1-148, Wells CountySolar + storage Β· 159 MW Β· withdrawn
- Solar project AH2-237, Wells CountySolar Β· 125 MW Β· withdrawn
- Solar project AG2-638, Wells CountySolar Β· 100 MW Β· withdrawn
- Battery storage project Y2-112, Wells CountyBattery storage Β· 12.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem