SOLAR + STORAGE Β· PJM

Solar + storage project AF1-148, Wells County

Solar + storage project AF1-148, Wells County is a 159 MW solar + storage request withdrawn in the PJM interconnection queue, in Wells County, Indiana, connecting to AEP.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2019 (completed)
  2. Withdrawn / abandonedNov 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AF1-148
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Sorenson-Desoto 345 kV
Location
Wells County, Indiana
Technology
Solar: 159 MW Β· Battery
Total requested
159 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study
Queue status
Withdrawn
Entered queue
19 September 2019
Proposed online date
April 2023
Withdrawn
November 2024

Location

Marker shows the centre of Wells County; the queue data does not give exact sites.

Power plants in Indiana Β· Transmission lines in Indiana

Other requests in Wells County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem