OCTARY USA · INTERCONNECTION QUEUESWithdrawn queue requests in NYISO (New York) (2017 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Liberty Generating Alternative Gas · North Bergen Liberty Generating, LLC |
1,172 MW | Withdrawn / abandoned |
| Franklin Solar Solar · Franklin Solar, LLC |
150 MW | Withdrawn / abandoned |
| Coldwater Solar Solar · EDP Renewables North America LLC |
80.0 MW | Withdrawn / abandoned |
| Helix Ravenswood II Gas · LS Power Development, LLC |
72.4 MW | Withdrawn / abandoned |
| Keesog Solar Solar · Cypress Creek Renewables |
50.0 MW | Withdrawn / abandoned |
| Linden Cogen Uprate Gas · East Coast Power LLC |
32.0 MW | Withdrawn / abandoned |
| Helix Ravenswood I Gas · LS Power Development, LLC |
30.2 MW | Withdrawn / abandoned |
| Daybreak Solar Solar · Daybreak Solar, LLC |
25.0 MW | Withdrawn / abandoned |
| Silver Lake Solar Solar · Silver Lake Solar, LLC |
24.9 MW | Withdrawn / abandoned |
| Mohawk Solar Solar · Heelstone Development, LLC |
20.0 MW | Withdrawn / abandoned |
| Rising Solar Solar · Rising Solar, LLC |
20.0 MW | Withdrawn / abandoned |
| Clay Solar Solar · SED NY Holdings LLC |
20.0 MW | Withdrawn / abandoned |
| Grissom Solar Solar · Granada Solar, LLC |
20.0 MW | Withdrawn / abandoned |
| Whitehart Solar Solar · Whitehart Solar, LLC |
20.0 MW | Withdrawn / abandoned |
| Alcoa Solar Solar · Geronimo Solar Energy, LLC |
20.0 MW | Withdrawn / abandoned |
| South Cooper Solar Solar · South Cooper Solar LLC |
20.0 MW | Withdrawn / abandoned |
| Woodruff Solar Solar · Woodruff Solar, LLC |
20.0 MW | Withdrawn / abandoned |
| Forest Glen Solar Solar · Forest Glen Solar LLC |
20.0 MW | Withdrawn / abandoned |
| Admiral Wind LLC Onshore wind · Admiral Wind LLC |
20.0 MW | Withdrawn / abandoned |
| Sugar Maple Solar Solar · OneEnergy Development, LLC |
20.0 MW | Withdrawn / abandoned |
| Grange Solar Solar · Granada Solar, LLC |
20.0 MW | Withdrawn / abandoned |
| Kce NY 1 Other · KCE NY 1, LLC |
20.0 MW | Withdrawn / abandoned |
| Manny Corner Solar Solar · Oya Solar NY LP |
20.0 MW | Withdrawn / abandoned |
| Bakerstand Solar Solar · Bakerstand Solar LLC |
20.0 MW | Withdrawn / abandoned |
| Champagne Storage Battery storage · Champagne Storage, LLC |
20.0 MW | Withdrawn / abandoned |
| Martin Rd Solar Solar · Martin Rd Solar LLC |
20.0 MW | Withdrawn / abandoned |
| Shaw Solar Solar · Oya Solar NY LP |
20.0 MW | Withdrawn / abandoned |
| Mistral Wind LLC Onshore wind · Mistral Wind LLC |
20.0 MW | Withdrawn / abandoned |
| Black Creek Solar Solar · Oya Solar NY LP |
20.0 MW | Withdrawn / abandoned |
| Taku Wind Onshore wind · Taku Wind LLC |
20.0 MW | Withdrawn / abandoned |
| Cayuga Solar Solar · Cayuga Operating Co. |
20.0 MW | Withdrawn / abandoned |
| Slingshot 2 Solar Solar · OneEnergy Development, LLC |
20.0 MW | Withdrawn / abandoned |
| Southtown 2 Solar Solar · OneEnergy Development, LLC |
20.0 MW | Withdrawn / abandoned |
| Greene County 3 Solar · Hecate Energy Greene County 3 LLC |
20.0 MW | Withdrawn / abandoned |
| Janis Solar Solar · Conti Enterprises, Inc. |
20.0 MW | Withdrawn / abandoned |
| Robinson Solar Solar · Oya Solar NY LP |
20.0 MW | Withdrawn / abandoned |
| Columbia County 1 Solar · Hecate Energy Columbia County 1, LLC |
20.0 MW | Withdrawn / abandoned |
| Sabertooth Solar Solar · Sabertooth Solar, LLC |
20.0 MW | Withdrawn / abandoned |
| Regan Solar Solar · Granada Solar, LLC |
20.0 MW | Withdrawn / abandoned |
| LeRoy Solar Solar · LeRoy, LLC |
20.0 MW | Withdrawn / abandoned |
| Badra Solar Solar · Badra Solar, LLC |
20.0 MW | Withdrawn / abandoned |
| Columbia County 2 Solar · Hecate Energy Columbia County 2, LLC |
20.0 MW | Withdrawn / abandoned |
| Saugerties Solar Solar · Blue Stone Solar Energy, LLC |
20.0 MW | Withdrawn / abandoned |
| Puckett Solar Solar · Conti Enterprises, Inc. |
20.0 MW | Withdrawn / abandoned |
| Owego Solar Solar · Owego Solar LLC |
20.0 MW | Withdrawn / abandoned |
| Moffitt Solar Solar · Plattsburgh Solar, LLC |
20.0 MW | Withdrawn / abandoned |
| Darby Solar Solar · Conti Enterprises, Inc. |
20.0 MW | Withdrawn / abandoned |
| Somerset Solar Solar · Somerset Operating Company LLC |
19.9 MW | Withdrawn / abandoned |
| Volney Solar Park Solar · CVE North America, Inc. |
19.8 MW | Withdrawn / abandoned |
| Brookhaven Rail Terminal Battery storage · BRT Fuel Cell, LLC |
18.5 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)302 · 46.9 GW
- SPP (Southwest Power Pool)162 · 32.0 GW
- MISO (Midcontinent)127 · 19.9 GW
- PJM (Mid-Atlantic, Midwest)236 · 18.3 GW
- Southeast (non-ISO utilities)208 · 16.9 GW
- CAISO (California)65 · 11.3 GW
- ERCOT (Texas)55 · 8,908 MW
- ISO-NE (New England)42 · 4,856 MW
- NYISO (New York)61 · 2,565 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)