Manny Corner Solar

Manny Corner Solar is a 20.0 MW solar request withdrawn in the NYISO interconnection queue, in Montgomery County, New York, connecting to NM-NG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2017 (completed)
  2. Withdrawn / abandonedMar 2018 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
645
Grid region
NYISO (New York)
Utility / transmission owner
NM-NG
Developer
Oya Solar NY LP
Connection point (POI)
Meco - Rotterdam 115kV
Location
Montgomery County, New York
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Queue status
Withdrawn
Entered queue
1 August 2017
Withdrawn
March 2018

Location

Marker shows the centre of Montgomery County; the queue data does not give exact sites.