United States βΊ Grid βΊ Interconnection queues βΊ New York
SOLAR Β· NYISOKeesog Solar
Keesog Solar is a 50.0 MW solar request withdrawn in the NYISO interconnection queue, in Franklin County, New York, connecting to NYPA.
Queue statusWithdrawn / abandoned
- PlanningQueued Jan 2017 (completed)
- Withdrawn / abandonedMay 2017 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 602
- Grid region
- NYISO (New York)
- Utility / transmission owner
- NYPA
- Developer
- Cypress Creek Renewables
- Connection point (POI)
- Moses - Willis 230kV
- Location
- Franklin County, New York
- Technology
- Solar: 50.0 MW
- Total requested
- 50.0 MW
- Queue status
- Withdrawn
- Entered queue
- 30 January 2017
- Withdrawn
- May 2017
Location
Marker shows the centre of Franklin County; the queue data does not give exact sites.
Other requests in Franklin County
- North Country WindOnshore wind Β· 380 MW Β· in study
- North Country Wind IIOnshore wind Β· 380 MW Β· in study
- NY125A - Fort Covington SolarSolar Β· 250 MW Β· in study
- NY125C - Little Salmon SolarSolar Β· 200 MW Β· in study
- NY Chateaugay 0 Willis Rd Storage (NYISO-C24-304-004)Battery storage Β· 150 MW Β· in study
- NY Chateaugay 0 Willis Rd StorageBattery storage Β· 150 MW Β· in study
- Jericho SolarSolar Β· 100 MW Β· in study
- Brookside SolarSolar Β· 100 MW Β· in study
- Chateaugay WindparkOnshore wind Β· 107 MW Β· built
- Jericho Rise WindOnshore wind Β· 77.7 MW Β· built
- Jericho Rise WindOnshore wind Β· 77.7 MW Β· built
- North County Energy StorageBattery storage Β· 20.0 MW Β· built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem