United States βΊ Grid βΊ Interconnection queues βΊ New York
GAS Β· NYISOHelix Ravenswood II
Helix Ravenswood II is a 72.4 MW gas request withdrawn in the NYISO interconnection queue, in New York County, New York, connecting to ConEd.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2017 (completed)
- Withdrawn / abandonedSep 2018 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 673
- Grid region
- NYISO (New York)
- Utility / transmission owner
- ConEd
- Developer
- LS Power Development, LLC
- Connection point (POI)
- Rainey Substation 345kV
- Location
- New York County, New York
- Technology
- Gas: 72.4 MW
- Total requested
- 72.4 MW
- Queue status
- Withdrawn
- Entered queue
- 6 October 2017
- Withdrawn
- September 2018
Location
Marker shows the centre of New York County; the queue data does not give exact sites.
Other requests in New York County
- East River RepoweringGas Β· 288 MW Β· built
- East River RepoweringGas Β· 288 MW Β· built
- KeySpan RavenswoodGas Β· 270 MW Β· built
- KeySpan RavenswoodGas Β· 270 MW Β· built
- Hell GateGas Β· 79.9 MW Β· built
- Harlem River YardsGas Β· 79.9 MW Β· built
- Harlem River YardsGas Β· 79.9 MW Β· built
- Hell GateGas Β· 79.9 MW Β· built
- Vernon BlvdGas Β· 79.9 MW Β· built
- Vernon BlvdGas Β· 79.9 MW Β· built
- 23rd St and 3rd AveGas Β· 79.9 MW Β· built
- 23rd St and 3rd AveGas Β· 79.9 MW Β· built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem