πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί New York

SOLAR Β· NYISO

Grissom Solar

Grissom Solar is a 20.0 MW solar request withdrawn in the NYISO interconnection queue, in Fulton County, New York, connecting to NM-NG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2017 (completed)
  2. Withdrawn / abandonedNov 2017 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
640
Grid region
NYISO (New York)
Utility / transmission owner
NM-NG
Developer
Granada Solar, LLC
Connection point (POI)
Vail Mills Substation 69kV
Location
Fulton County, New York
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Queue status
Withdrawn
Entered queue
19 July 2017
Withdrawn
November 2017

Location

Marker shows the centre of Fulton County; the queue data does not give exact sites.

Power plants in New York Β· Transmission lines in New York

Other requests in Fulton County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem