Liberty Generating Alternative

Liberty Generating Alternative is a 1,172 MW gas request withdrawn in the NYISO interconnection queue, in New York County, New York, connecting to ConEd.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2017 (completed)
  2. Withdrawn / abandonedMay 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
668
Grid region
NYISO (New York)
Utility / transmission owner
ConEd
Developer
North Bergen Liberty Generating, LLC
Connection point (POI)
West 49th St 345kV
Location
New York County, New York
Technology
Gas: 1,172 MW
Total requested
1,172 MW
Queue status
Withdrawn
Entered queue
15 September 2017
Withdrawn
May 2023

Location

Marker shows the centre of New York County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in New York County