SOLAR Β· NYISOJanis Solar
Janis Solar is a 20.0 MW solar request withdrawn in the NYISO interconnection queue, connecting to NYSEG.
Queue statusWithdrawn / abandoned
- PlanningQueued May 2017 (completed)
- Withdrawn / abandonedJun 2017 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 633
- Grid region
- NYISO (New York)
- Utility / transmission owner
- NYSEG
- Developer
- Conti Enterprises, Inc.
- Connection point (POI)
- Willet - Tarbell 34.5 kV
- Location
- New York
- Technology
- Solar: 20.0 MW
- Total requested
- 20.0 MW
- Queue status
- Withdrawn
- Entered queue
- 15 May 2017
- Withdrawn
- June 2017