Gas project J3799, Livingston County Gas |
1,452 MW | In study |
Livingston, MI | MISO |
Apr 2024 | target 2030 |
Replacing 464.5 MW Steam/Gas with 97.8 MW Steam; DOW Chem Gas |
1,232 MW | In study |
Iberville, LA | MISO |
May 2024 | target 2025 |
Replacement; Oak Creek Units 5-8 Gas |
1,138 MW | In study |
Milwaukee, WI | MISO |
Jun 2024 | target 2027 |
Replacing 1014.7 MW of coal generation with Gas/Steam; Cayuga CC1 CC2 Gas |
1,040 MW | In study |
Vermillion, IN | MISO |
Feb 2024 | target 2028 |
Replacing 864 MW of coal with Natural Gas Generators; Castle Bluff Gas |
824 MW | In study |
St. Louis, MO | MISO |
May 2024 | target 2025 |
Gas project J3829, Hot Spring County Gas |
770 MW | In study |
Hot Spring, AR | MISO |
Apr 2024 | target 2028 |
Gas project J3874, Union County Gas |
770 MW | In study |
Union, AR | MISO |
Dec 2024 | target 2028 |
Replacing 722 MW Coal with 285 MW of Battery and 437MW of Gas; Schahfer Gas |
733 MW | In study |
Jasper, IN | MISO |
Dec 2024 | target 2027 |
Gas project J3604, Sullivan County Gas |
650 MW | In study |
Sullivan, IN | MISO |
Apr 2024 | target 2027 |
Replacing 615 MW Coal with 615 MW BESS; Campbell Units 1 & 2 Other |
615 MW | In study |
| MISO |
Jun 2024 | target 2028 |
Surplus; Big Bend Wind + storage |
550 MW | In study |
Cottonwood, MN | MISO |
Jul 2024 | target 2027 |
Gas project J3232, Vermillion County Gas |
500 MW | In study |
Vermillion, IN | MISO |
Apr 2024 | target 2028 |
Solar project J3401, Mississippi County Solar |
500 MW | In study |
Mississippi, AR | MISO |
Apr 2024 | target 2028 |
Solar project J3532, Roseau County Solar |
500 MW | In study |
Roseau, MN | MISO |
Apr 2024 | target 2028 |
Gas project J3331, Sullivan County Gas |
470 MW | In study |
Sullivan, IN | MISO |
Apr 2024 | target 2028 |
Onshore wind project J3730, Macoupin County Onshore wind |
444 MW | In study |
Macoupin, IL | MISO |
Apr 2024 | target 2028 |
Solar project J3762, Clay County Solar |
430 MW | In study |
Clay, MN | MISO |
Apr 2024 | target 2028 |
Onshore wind project J3712, Peoria County Onshore wind |
400 MW | In study |
Peoria, IL | MISO |
Apr 2024 | target 2028 |
Onshore wind project J3701, Taylor County Onshore wind |
400 MW | In study |
Taylor, IA | MISO |
Apr 2024 | target 2028 |
Solar + storage project J3591, St. Helena Parish County Solar + storage |
400 MW | In study |
St. Helena Parish, LA | MISO |
Apr 2024 | target 2028 |
Gas project J3666, Morgan County Gas |
379 MW | In study |
Morgan, IN | MISO |
Apr 2024 | target 2028 |
Surplus; Glacier Moraine Other |
360 MW | In study |
Cumberland, IL | MISO |
Jul 2024 | target 2027 |
Onshore wind project J3623, Sunflower County Onshore wind |
350 MW | In study |
Sunflower, MS | MISO |
Apr 2024 | target 2028 |
Onshore wind project J3521, Shelby County Onshore wind |
350 MW | In study |
Shelby, IL | MISO |
Apr 2024 | target 2028 |
Onshore wind project J3597, Lonoke County Onshore wind |
348 MW | In study |
Lonoke, AR | MISO |
Apr 2024 | target 2028 |
Replacing 106 MW Coal with 106 MW BESS; Edwards Unit 3 Other |
322 MW | In study |
Peoria, IL | MISO |
Jul 2024 | target 2025 |
Onshore wind project J3798, Winnebago County Onshore wind |
320 MW | In study |
Winnebago, IA | MISO |
Mar 2024 | target 2028 |
Onshore wind project J3982, Lonoke County Onshore wind |
320 MW | In study |
Lonoke, AR | MISO |
Dec 2024 | target 2030 |
Replacing 303.5 MW BESS with 303.5 MW COAL; Edgewater Unit 5 Other |
304 MW | In study |
Sheboygan, WI | MISO |
Dec 2024 | target 2025 |
Solar project J3498, Knox County Solar |
300 MW | In study |
Knox, IL | MISO |
Apr 2024 | target 2028 |
Battery storage project J3840, St. Landry Parish County Battery storage |
300 MW | In study |
St. Landry Parish, LA | MISO |
Dec 2024 | target 2030 |
Solar project J3454, Morehouse Parish County Solar |
300 MW | In study |
Morehouse Parish, LA | MISO |
Apr 2024 | target 2028 |
Onshore wind project J3699, Henry County Onshore wind |
300 MW | In study |
Henry, IL | MISO |
Apr 2024 | target 2028 |
Battery storage project J3518, Gasconade County Battery storage |
300 MW | In study |
Gasconade, MO | MISO |
Apr 2024 | target 2028 |
Onshore wind project J3681, Mclean County Onshore wind |
300 MW | In study |
Mclean, IL | MISO |
Apr 2024 | target 2028 |
Battery storage project J2377, Peoria County Battery storage |
300 MW | In study |
Peoria, IL | MISO |
Nov 2024 | target 2028 |
Onshore wind project J3866, Lapeer County Onshore wind |
300 MW | In study |
Lapeer, MI | MISO |
Dec 2024 | target 2028 |
Solar project J3399, Goodhue County Solar |
300 MW | In study |
Goodhue, MN | MISO |
Apr 2024 | target 2028 |
Solar project J3843, Saginaw County Solar |
300 MW | In study |
Saginaw, MI | MISO |
Nov 2024 | target 2027 |
Solar project J3723, Wexford County Solar |
300 MW | In study |
Wexford, MI | MISO |
Apr 2024 | target 2028 |
Wind + storage project J3468, Day County Wind + storage |
300 MW | In study |
Day, SD | MISO |
Apr 2024 | target 2028 |
Solar project J3412, Ford County Solar |
300 MW | In study |
Ford, IL | MISO |
Mar 2024 | target 2028 |
Battery storage project J3558, Champaign County Battery storage |
300 MW | In study |
Champaign, IL | MISO |
Apr 2024 | target 2027 |
Battery storage project J3525, Rock Island County Battery storage |
300 MW | In study |
Rock Island, IL | MISO |
Apr 2024 | target 2028 |
Onshore wind project J3384, Big Stone County Onshore wind |
300 MW | In study |
Big Stone, MN | MISO |
Apr 2024 | target 2028 |
Onshore wind project J3853, Iroquois County Onshore wind |
300 MW | In study |
Iroquois, IL | MISO |
Dec 2024 | target 2029 |
Battery storage project J3834, Gibson County Battery storage |
300 MW | In study |
Gibson, IN | MISO |
Sep 2024 | target 2026 |
Solar project J3758, Macon County Solar |
300 MW | In study |
Macon, MO | MISO |
Apr 2024 | target 2028 |
Onshore wind project J3672, Big Stone County Onshore wind |
300 MW | In study |
Big Stone, MN | MISO |
Apr 2024 | target 2028 |
Solar project J3669, Stevens County Solar |
300 MW | In study |
Stevens, MN | MISO |
Apr 2024 | target 2028 |