Withdrawn queue requests in MISO (Midcontinent) (2022 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown56794.5 GW
Active in queue82.2 GW435 requests
Agreement signed881 MW6 requests
Withdrawn56794.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

567 requests Β· page 1 of 12
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project J2911, Beauregard Parish County
Solar + storage
810 MWWithdrawn / abandoned Beauregard Parish, LAMISO Sep 2022target 2027
Gas project J3089, Webster County
Gas
696 MWWithdrawn / abandoned Webster, KYMISO Sep 2022target 2029
Solar project J2595, Hinds County
Solar
650 MWWithdrawn / abandoned Hinds, MSMISO Sep 2022target 2026
Solar project J2594, Hinds County
Solar
650 MWWithdrawn / abandoned Hinds, MSMISO Sep 2022target 2026
Solar + storage project J2717, Hot Spring County
Solar + storage
600 MWWithdrawn / abandoned Hot Spring, ARMISO Sep 2022target 2029
Gas project J3215, Laporte County
Gas
594 MWWithdrawn / abandoned Laporte, INMISO Sep 2022target 2025
Other project J2697, St. Clair County
Other
500 MWWithdrawn / abandoned St. Clair, ILMISO Sep 2022target 2027
Solar project J2785, Calhoun County
Solar
500 MWWithdrawn / abandoned Calhoun, ARMISO Sep 2022target 2026
Onshore wind project J2698, Choctaw County
Onshore wind
500 MWWithdrawn / abandoned Choctaw, MSMISO Sep 2022target 2028
Solar project J2758, Jefferson County
Solar
500 MWWithdrawn / abandoned Jefferson, ARMISO Sep 2022target 2025
Solar project J2706, Morehouse Parish County
Solar
500 MWWithdrawn / abandoned Morehouse Parish, LAMISO Sep 2022target 2027
Battery storage project J2443, Kosciusko County
Battery storage
500 MWWithdrawn / abandoned Kosciusko, INMISO Sep 2022target 2025
Other project J2692, Choctaw County
Other
500 MWWithdrawn / abandoned Choctaw, MSMISO Sep 2022target 2028
Solar project J2399, Craighead County
Solar
500 MWWithdrawn / abandoned Craighead, ARMISO Sep 2022target 2025
Solar project J3032, Webster Parish County
Solar
500 MWWithdrawn / abandoned Webster Parish, LAMISO Sep 2022target 2026
Solar project J2888, Lafayette Parish County
Solar
500 MWWithdrawn / abandoned Lafayette Parish, LAMISO Sep 2022target 2026
Solar + storage project J3106, Pemiscot County
Solar + storage
500 MWWithdrawn / abandoned Pemiscot, MOMISO Sep 2022target 2025
Solar project J2682, Jackson County
Solar
500 MWWithdrawn / abandoned Jackson, ARMISO Sep 2022target 2025
Solar project J2452, Cleveland County
Solar
500 MWWithdrawn / abandoned Cleveland, ARMISO Sep 2022target 2026
Solar + storage project J2856, Jefferson County
Solar + storage
500 MWWithdrawn / abandoned Jefferson, MSMISO Sep 2022target 2024
Solar project J2936, Jackson County
Solar
500 MWWithdrawn / abandoned Jackson, ARMISO Sep 2022target 2025
Onshore wind project J2591, Choctaw County
Onshore wind
500 MWWithdrawn / abandoned Choctaw, MSMISO Sep 2022target 2028
Solar + storage project J3102, Pemiscot County
Solar + storage
500 MWWithdrawn / abandoned Pemiscot, MOMISO Sep 2022target 2025
Battery storage project J2624, Stevens County
Battery storage
450 MWWithdrawn / abandoned Stevens, MNMISO Sep 2022target 2026
Solar + storage project J2890, Calcasieu Parish County
Solar + storage
440 MWWithdrawn / abandoned Calcasieu Parish, LAMISO Sep 2022target 2027
Solar + storage project J2882, Beauregard Parish County
Solar + storage
410 MWWithdrawn / abandoned Beauregard Parish, LAMISO Sep 2022target 2027
Solar project J2916, Rapides Parish County
Solar
400 MWWithdrawn / abandoned Rapides Parish, LAMISO Sep 2022target 2026
Battery storage project J3023, Hot Spring County
Battery storage
400 MWWithdrawn / abandoned Hot Spring, ARMISO Sep 2022target 2026
Solar + storage project J2900, Amite County
Solar + storage
400 MWWithdrawn / abandoned Amite, MSMISO Sep 2022target 2026
Solar + storage project J2953, Orange County
Solar + storage
400 MWWithdrawn / abandoned Orange, TXMISO Sep 2022target 2026
Solar + storage project J3105, Amite County
Solar + storage
400 MWWithdrawn / abandoned Amite, MSMISO Sep 2022target 2025
Battery storage project J3022, Taylor County
Battery storage
400 MWWithdrawn / abandoned Taylor, IAMISO Sep 2022target 2026
Solar + storage project J3110, Craighead County
Solar + storage
400 MWWithdrawn / abandoned Craighead, ARMISO Sep 2022target 2026
Solar project J2703, Scott County
Solar
398 MWWithdrawn / abandoned Scott, ILMISO Sep 2022target 2027
Solar project J2640, Calhoun County
Solar
395 MWWithdrawn / abandoned Calhoun, ARMISO Sep 2022target 2025
Solar project J2579, Tazewell County
Solar
362 MWWithdrawn / abandoned Tazewell, ILMISO Sep 2022target 2027
Battery storage project J2606, Steele County
Battery storage
361 MWWithdrawn / abandoned Steele, NDMISO Sep 2022target 2027
Solar project J2510, Jefferson County
Solar
350 MWWithdrawn / abandoned Jefferson, ARMISO Sep 2022target 2026
Solar + storage project J3119, Pulaski County
Solar + storage
350 MWWithdrawn / abandoned Pulaski, INMISO Sep 2022target 2026
Solar + storage project J2883, Mercer County
Solar + storage
347 MWWithdrawn / abandoned Mercer, NDMISO Sep 2022target 2027
Solar + storage project J2665, Mercer County
Solar + storage
347 MWWithdrawn / abandoned Mercer, NDMISO Sep 2022target 2027
Solar + storage project J2912, Mercer County
Solar + storage
347 MWWithdrawn / abandoned Mercer, NDMISO Sep 2022target 2027
Onshore wind project J2605, Steele County
Onshore wind
339 MWWithdrawn / abandoned Steele, NDMISO Sep 2022target 2027
Onshore wind project J2910, Chambers County
Onshore wind
303 MWWithdrawn / abandoned Chambers, TXMISO Sep 2022target 2026
Onshore wind project J2481, Pocahontas County
Onshore wind
300 MWWithdrawn / abandoned Pocahontas, IAMISO Sep 2022target 2030
Gas project J3052, Midland County
Gas
300 MWWithdrawn / abandoned Midland, MIMISO Sep 2022target 1990
Solar project J2269, Fountain County
Solar
300 MWWithdrawn / abandoned Fountain, INMISO Jun 2022target 2024
Battery storage project J2497, Jefferson County
Battery storage
300 MWWithdrawn / abandoned Jefferson, ILMISO Sep 2022target 2026
Solar project J2516, Jefferson County
Solar
300 MWWithdrawn / abandoned Jefferson, ARMISO Sep 2022target 2026
Battery storage project J2790, Christian County
Battery storage
300 MWWithdrawn / abandoned Christian, ILMISO Sep 2022target 2026
Page 1 of 12

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)