ONSHORE WIND Β· MISO

Onshore wind project J2605, Steele County

Onshore wind project J2605, Steele County is a 339 MW onshore wind request withdrawn in the MISO interconnection queue, in Steele County, North Dakota, connecting to MISSOURI RIVER ENERGY SERVICES - TRANSMISSION.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2022 (completed)
  2. Withdrawn / abandonedOct 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2605
Grid region
MISO (Midcontinent)
Utility / transmission owner
MISSOURI RIVER ENERGY SERVICES - TRANSMISSION
Connection point (POI)
ALEXANDRIA 345 KV
Location
Steele County, North Dakota
Technology
Wind: 339 MW
Total requested
339 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
15 September 2022
Proposed online date
June 2027
Withdrawn
October 2025

Location

Marker shows the centre of Steele County; the queue data does not give exact sites.