United States βΊ Grid βΊ Interconnection queues βΊ North Dakota
ONSHORE WIND Β· MISOOnshore wind project J2605, Steele County
Onshore wind project J2605, Steele County is a 339 MW onshore wind request withdrawn in the MISO interconnection queue, in Steele County, North Dakota, connecting to MISSOURI RIVER ENERGY SERVICES - TRANSMISSION.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2022 (completed)
- Withdrawn / abandonedOct 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J2605
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- MISSOURI RIVER ENERGY SERVICES - TRANSMISSION
- Connection point (POI)
- ALEXANDRIA 345 KV
- Location
- Steele County, North Dakota
- Technology
- Wind: 339 MW
- Total requested
- 339 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 15 September 2022
- Proposed online date
- June 2027
- Withdrawn
- October 2025
Location
Marker shows the centre of Steele County; the queue data does not give exact sites.
Power plants in North Dakota Β· Transmission lines in North Dakota
Other requests in Steele County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem