United States β€Ί Grid β€Ί Interconnection queues β€Ί Arkansas

SOLAR + STORAGE Β· MISO

Solar + storage project J2717, Hot Spring County

Solar + storage project J2717, Hot Spring County is a 600 MW solar + storage request withdrawn in the MISO interconnection queue, in Hot Spring County, Arkansas, connecting to ENTERGY ARKANSAS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2022 (completed)
  2. Withdrawn / abandonedOct 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2717
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY ARKANSAS
Connection point (POI)
ETTA 500kV Substation
Location
Hot Spring County, Arkansas
Technology
Solar: 600 MW Β· Battery
Total requested
600 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
15 September 2022
Proposed online date
May 2029
Withdrawn
October 2023

Location

Marker shows the centre of Hot Spring County; the queue data does not give exact sites.

Power plants in Arkansas Β· Transmission lines in Arkansas

Other requests in Hot Spring County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem