United States βΊ Grid βΊ Interconnection queues
OCTARY USA Β· INTERCONNECTION QUEUESWithdrawn queue requests in MISO (Midcontinent) (2013 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Gas project J268, Genesee County Gas |
801 MW | Withdrawn / abandoned |
| Gas project J275, Midland County Gas |
700 MW | Withdrawn / abandoned |
| Gas project J294, Brown County Gas |
588 MW | Withdrawn / abandoned |
| Other project J319, Pope County Other |
500 MW | Withdrawn / abandoned |
| Gas project J293, Outagamie County Gas |
496 MW | Withdrawn / abandoned |
| Gas project J284, Dakota County Gas |
316 MW | Withdrawn / abandoned |
| Onshore wind project J308, Sanilac County Onshore wind |
301 MW | Withdrawn / abandoned |
| Onshore wind project J298, Tama County Onshore wind |
300 MW | Withdrawn / abandoned |
| Gas project J271, Montcalm County Gas |
232 MW | Withdrawn / abandoned |
| Gas project J280, Goodhue County Gas |
221 MW | Withdrawn / abandoned |
| Onshore wind project J312, Clinton County Onshore wind |
201 MW | Withdrawn / abandoned |
| Onshore wind project J313, Montgomery County Onshore wind |
201 MW | Withdrawn / abandoned |
| Onshore wind project J311, Nodaway County Onshore wind |
201 MW | Withdrawn / abandoned |
| Onshore wind project J307, Osceola County Onshore wind |
201 MW | Withdrawn / abandoned |
| Onshore wind project J286, Audubon County Onshore wind |
199 MW | Withdrawn / abandoned |
| Onshore wind project J054, Tipton County Onshore wind |
198 MW | Withdrawn / abandoned |
| Onshore wind project J270, Newton County Onshore wind |
198 MW | Withdrawn / abandoned |
| Onshore wind project J272, Poweshiek County Onshore wind |
170 MW | Withdrawn / abandoned |
| Onshore wind project J277, Iroquois County Onshore wind |
150 MW | Withdrawn / abandoned |
| Wind + storage project J276, Iroquois County Wind + storage |
150 MW | Withdrawn / abandoned |
| Onshore wind project J297, O'brien County Onshore wind |
150 MW | Withdrawn / abandoned |
| Onshore wind project J273, Dewitt County Onshore wind |
150 MW | Withdrawn / abandoned |
| Onshore wind project J267, Tuscola County Onshore wind |
125 MW | Withdrawn / abandoned |
| Gas project J317, Marquette County Gas |
112 MW | Withdrawn / abandoned |
| Onshore wind project J306, Traverse County Onshore wind |
101 MW | Withdrawn / abandoned |
| Onshore wind project J314, Columbia County Onshore wind |
101 MW | Withdrawn / abandoned |
| Onshore wind project J315, Rock County Onshore wind |
101 MW | Withdrawn / abandoned |
| Onshore wind project J296, Presque Isle County Onshore wind |
69.3 MW | Withdrawn / abandoned |
| Onshore wind project J300, Mackinac County Onshore wind |
60.0 MW | Withdrawn / abandoned |
| Onshore wind project J287, Nobles County Onshore wind |
56.7 MW | Withdrawn / abandoned |
| Gas project J295, Lyon County Gas |
50.0 MW | Withdrawn / abandoned |
| Onshore wind project J281, Huron County Onshore wind |
50.0 MW | Withdrawn / abandoned |
| Onshore wind project J282, Huron County Onshore wind |
50.0 MW | Withdrawn / abandoned |
| Onshore wind project J118, Greene County Onshore wind |
50.0 MW | Withdrawn / abandoned |
| Solar project J305, Lyon County Solar |
50.0 MW | Withdrawn / abandoned |
| Onshore wind project J288, Kandiyohi County Onshore wind |
40.0 MW | Withdrawn / abandoned |
| Onshore wind project J318, Morgan County Onshore wind |
30.0 MW | Withdrawn / abandoned |
| Coal project J269, Columbia County Coal |
26.0 MW | Withdrawn / abandoned |
| Solar project J304, Dakota County Solar |
20.0 MW | Withdrawn / abandoned |
| Onshore wind project J283, Cottonwood County Onshore wind |
20.0 MW | Withdrawn / abandoned |
| Solar project J309, Yellow Medicine County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project J303, Murray County Solar |
20.0 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)136 Β· 10.7 GW
- PJM (Mid-Atlantic, Midwest)80 Β· 10.3 GW
- ERCOT (Texas)52 Β· 8,996 MW
- MISO (Midcontinent)42 Β· 7,775 MW
- CAISO (California)47 Β· 7,426 MW
- SPP (Southwest Power Pool)30 Β· 4,501 MW
- Southeast (non-ISO utilities)62 Β· 4,349 MW
- NYISO (New York)4 Β· 953 MW
- ISO-NE (New England)9 Β· 840 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)