WIND + STORAGE Β· MISO

Wind + storage project J276, Iroquois County

Wind + storage project J276, Iroquois County is a 150 MW wind + storage request withdrawn in the MISO interconnection queue, in Iroquois County, Illinois.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2013 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. ConsentedFeb 2015 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J276
Grid region
MISO (Midcontinent)
Connection point (POI)
Sheldon South
Location
Iroquois County, Illinois
Technology
Wind: 150 MW Β· Battery
Total requested
150 MW
Study phase
DPP - SIS
Queue status
Withdrawn
Entered queue
18 March 2013
Agreement signed
19 February 2015
Proposed online date
August 2014

Location

Marker shows the centre of Iroquois County; the queue data does not give exact sites.

Power plants in Illinois Β· Transmission lines in Illinois

Other requests in Iroquois County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem