ONSHORE WIND Β· MISOOnshore wind project J281, Huron County
Onshore wind project J281, Huron County is a 50.0 MW onshore wind request withdrawn in the MISO interconnection queue, in Huron County, Michigan.
Queue statusWithdrawn / abandoned
- PlanningQueued May 2013 (completed)
- Withdrawn / abandonedMay 2015 (project stopped here)
- ConsentedMar 2014 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J281
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Cosmo-Harvest Wind 120 kV circuit near Cosmo subst
- Location
- Huron County, Michigan
- Technology
- Wind: 50.0 MW
- Total requested
- 50.0 MW
- Study phase
- Optional
- Queue status
- Withdrawn
- Entered queue
- 17 May 2013
- Agreement signed
- 25 March 2014
- Proposed online date
- November 2013
- Withdrawn
- May 2015
Location
Marker shows the centre of Huron County; the queue data does not give exact sites.
Other requests in Huron County
- Solar project J1525, Huron CountySolar Β· 200 MW Β· agreement signed
- Battery storage project J466, Huron CountyBattery storage Β· 30.0 MW Β· agreement signed
- Battery storage project J2590, Huron CountyBattery storage Β· 500 MW Β· in study
- Onshore wind project J3966, Huron CountyOnshore wind Β· 480 MW Β· in study
- Onshore wind project J4203, Huron CountyOnshore wind Β· 350 MW Β· in study
- Battery storage project J4095, Huron CountyBattery storage Β· 300 MW Β· in study
- Battery storage project J4094, Huron CountyBattery storage Β· 300 MW Β· in study
- Onshore wind project J3971, Huron CountyOnshore wind Β· 255 MW Β· in study
- Battery storage project J2628, Huron CountyBattery storage Β· 250 MW Β· in study
- Battery storage project J4058, Huron CountyBattery storage Β· 250 MW Β· in study
- Solar project J2676, Huron CountySolar Β· 200 MW Β· in study
- Onshore wind project J3967, Huron CountyOnshore wind Β· 170 MW Β· in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem