ONSHORE WIND Β· MISO

Onshore wind project J272, Poweshiek County

Onshore wind project J272, Poweshiek County is a 170 MW onshore wind request withdrawn in the MISO interconnection queue, in Poweshiek County, Iowa.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2013 (completed)
  2. Withdrawn / abandonedNov 2014 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J272
Grid region
MISO (Midcontinent)
Connection point (POI)
Parnell - Poweshiek 161 kV
Location
Poweshiek County, Iowa
Technology
Wind: 170 MW
Total requested
170 MW
Study phase
Optional
Queue status
Withdrawn
Entered queue
7 March 2013
Withdrawn
November 2014

Location

Marker shows the centre of Poweshiek County; the queue data does not give exact sites.

Power plants in Iowa Β· Transmission lines in Iowa

Other requests in Poweshiek County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem