United States βΊ Grid βΊ Interconnection queues βΊ Iowa
ONSHORE WIND Β· MISOOnshore wind project R51, Poweshiek County
Onshore wind project R51, Poweshiek County is a 251 MW onshore wind request withdrawn in the MISO interconnection queue, in Poweshiek County, Iowa.
Queue statusWithdrawn / abandoned
- PlanningQueued Feb 2008 (completed)
- Withdrawn / abandonedMay 2011 (project stopped here)
- ConsentedMay 2011 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- R51
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Montezuma 345kV
- Location
- Poweshiek County, Iowa
- Technology
- Wind: 251 MW
- Total requested
- 251 MW
- Study phase
- DPP - SIS
- Queue status
- Withdrawn
- Entered queue
- 15 February 2008
- Agreement signed
- 18 May 2011
- Proposed online date
- August 2009
- Withdrawn
- May 2011
Location
Marker shows the centre of Poweshiek County; the queue data does not give exact sites.
Other requests in Poweshiek County
- Onshore wind project J475, Poweshiek CountyOnshore wind Β· 200 MW Β· built
- Onshore wind project J438, Poweshiek CountyOnshore wind Β· 170 MW Β· built
- Onshore wind project J555, Poweshiek CountyOnshore wind Β· 140 MW Β· built
- Onshore wind project J272, Poweshiek CountyOnshore wind Β· 170 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem