United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Completed queue projects in MISO (Midcontinent) (2018 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown151,749 MW
Active in queue10.3 GW61 requests
Agreement signed3,007 MW20 requests
Withdrawn16528.2 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

15 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J1182, Adair County
Solar
250 MWOperating Adair, MOMISO Mar 20182024
Onshore wind project J1050, Boone County
Onshore wind
225 MWOperating Boone, IAMISO Mar 20182022
Onshore wind project J1181, Chickasaw County
Onshore wind
200 MWOperating Chickasaw, IAMISO Mar 20182022
Onshore wind project J968, Jasper County
Onshore wind
200 MWOperating Jasper, INMISO Mar 20182023
Onshore wind project J1022, Mclean County
Onshore wind
150 MWOperating Mclean, ILMISO Mar 20182022
Solar project J1153, Sheboygan County
Solar
150 MWOperating Sheboygan, WIMISO Mar 20182022
Solar project J1030, Polk County
Solar
150 MWOperating Polk, TXMISO Mar 20182023
Onshore wind project J1055, Mason County
Onshore wind
144 MWOperating Mason, ILMISO Mar 20182020
Solar project J1002, Waushara County
Solar
99.0 MWOperating Waushara, WIMISO Mar 20182023
Solar project J1188, Rock County
Solar
50.0 MWOperating Rock, WIMISO Mar 20182022
Solar project J1003, Dodge County
Solar
50.0 MWOperating Dodge, WIMISO Mar 20182023
Solar project J1000, Grant County
Solar
50.0 MWOperating Grant, WIMISO Mar 20182023
Solar project J1142, St. James Parish County
Solar
20.0 MWOperating St. James Parish, LAMISO Mar 20182020
Coal project J1146, Mississippi County
Coal
10.0 MWOperating Mississippi, ARMISO Mar 20182020
Solar project J1183, Delta County
Solar
1.4 MWOperating Delta, MIMISO Mar 20182019

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)