United States › Grid › Interconnection queues › Iowa
ONSHORE WIND · MISOOnshore wind project J1181, Chickasaw County
Onshore wind project J1181, Chickasaw County is a 200 MW onshore wind request built and operating in the MISO interconnection queue, in Chickasaw County, Iowa, connecting to ITC MIDWEST.
Request details
- Queue ID
- J1181
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ITC MIDWEST
- Connection point (POI)
- Hazleton - Mitchell county 345 kV line
- Location
- Chickasaw County, Iowa
- Technology
- Wind: 200 MW
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: In Service
- Queue status
- Operational
- Entered queue
- 12 March 2018
- Agreement signed
- 15 June 2021
- Proposed online date
- October 2022
- Came online
- October 2022
Location
Marker shows the centre of Chickasaw County; the queue data does not give exact sites.
Other requests in Chickasaw County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem