United States βΊ Grid βΊ Interconnection queues
OCTARY USA Β· INTERCONNECTION QUEUESWithdrawn queue requests in ISO-NE (New England) (2016 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Combined Cycle Gas |
1,120 MW | Withdrawn / abandoned |
| Bay State Offshore Wind 1 Offshore wind |
800 MW | Withdrawn / abandoned |
| Combined Cycle Gas |
563 MW | Withdrawn / abandoned |
| Wind Onshore wind |
376 MW | Withdrawn / abandoned |
| Wind Onshore wind |
246 MW | Withdrawn / abandoned |
| Wind Onshore wind |
216 MW | Withdrawn / abandoned |
| Solar Solar |
150 MW | Withdrawn / abandoned |
| Combustion Turbine Gas |
102 MW | Withdrawn / abandoned |
| Solar Solar |
98.0 MW | Withdrawn / abandoned |
| Wind Onshore wind |
93.6 MW | Withdrawn / abandoned |
| Solar Solar |
78.4 MW | Withdrawn / abandoned |
| Solar Solar |
78.4 MW | Withdrawn / abandoned |
| Solar Solar |
75.0 MW | Withdrawn / abandoned |
| Steam Turbines Other |
75.0 MW | Withdrawn / abandoned |
| Combined Cycle GT Gas |
68.0 MW | Withdrawn / abandoned |
| Solar Solar |
65.0 MW | Withdrawn / abandoned |
| Solar Solar |
63.0 MW | Withdrawn / abandoned |
| Combined Cycle Upgrade Gas |
40.0 MW | Withdrawn / abandoned |
| Hydro Hydro |
28.3 MW | Withdrawn / abandoned |
| Gas Turbine Upgrade Other |
23.5 MW | Withdrawn / abandoned |
| Combined Cycle Uprate Gas |
21.1 MW | Withdrawn / abandoned |
| Solar Solar |
19.9 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- MISO (Midcontinent)185 Β· 25.4 GW
- Southeast (non-ISO utilities)212 Β· 25.1 GW
- PJM (Mid-Atlantic, Midwest)250 Β· 23.8 GW
- West (non-ISO utilities)255 Β· 23.7 GW
- CAISO (California)96 Β· 19.6 GW
- SPP (Southwest Power Pool)110 Β· 19.5 GW
- ERCOT (Texas)39 Β· 7,318 MW
- ISO-NE (New England)22 Β· 4,400 MW
- NYISO (New York)25 Β· 2,046 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)