United States β€Ί Grid β€Ί Interconnection queues β€Ί Connecticut

SOLAR Β· ISO-NE

Solar

Solar is a 63.0 MW solar request withdrawn in the ISO-NE interconnection queue, in Windham County, Connecticut.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2016 (completed)
  2. Withdrawn / abandonedJul 2016 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
613
Grid region
ISO-NE (New England)
Connection point (POI)
Killingly to Tunnel 115 kV line
Location
Windham County, Connecticut
Technology
Solar: 63.0 MW
Total requested
63.0 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
28 June 2016
Proposed online date
July 2018
Withdrawn
July 2016

Location

No county location in the queue data.

Power plants in Connecticut Β· Transmission lines in Connecticut

Other requests in Windham County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem