United States β€Ί Grid β€Ί Interconnection queues β€Ί Maine

OCTARY USA Β· INTERCONNECTION QUEUES

Completed queue projects in Maine, ISO-NE

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown642,142 MW
Active in queue1,030 MW16 requests
Agreement signed850 MW15 requests
Withdrawn20419.0 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

64 requests Β· page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Bingham Wind
Onshore wind
185 MWOperating Somerset, MEISO-NE May 2010target 2016
Cross Town Battery Storage
Battery storage
175 MWOperating Cumberland, MEISO-NE Apr 2019target 2025
Oakfield II Wind - Keene Road
Onshore wind
136 MWOperating Aroostook, MEISO-NE Aug 2008target 2012
Millinocket Frequency Conversion
Hydro
126 MWOperating Penobscot, MEISO-NE Feb 2015target 2019
Great Northern - Millinocket
Hydro
126 MWOperating Penobscot, MEISO-NE Dec 2001target 2003
Millinocket Battery additon
Other
126 MWOperating Penobscot, MEISO-NE Apr 2019target 2020
Downeast Wind
Onshore wind
126 MWOperating Washington, MEISO-NE Apr 2018target 2024
Three Corners Solar
Solar
110 MWOperating Somerset, MEISO-NE Jul 2017target 2024
Farminton Solar
Solar
78.4 MWOperating Franklin, MEISO-NE Aug 2015target 2021
Weaver Wind
Onshore wind
72.6 MWOperating Hancock, MEISO-NE Jul 2013target 2020
Kibby Wind Project
Onshore wind
65.0 MWOperating Franklin, MEISO-NE Sep 2005target 2009
Western Maine Wind Project
Onshore wind
58.8 MWOperating Somerset, MEISO-NE May 2020target 2024
Hancock Wind Project
Onshore wind
51.0 MWOperating Hancock, MEISO-NE Aug 2012target 2016
Record Hill Wind
Onshore wind
50.6 MWOperating Oxford, MEISO-NE Jan 2007target 2012
Sanford Airport Solar
Solar
50.0 MWOperating York, MEISO-NE Dec 2015target 2020
Passadumkeag Windpark
Onshore wind
40.0 MWOperating Penobscot, MEISO-NE Feb 2011target 2016
Bull Hill Wind Phase I
Onshore wind
34.5 MWOperating Hancock, MEISO-NE Nov 2009target 2012
Saddleback Ridge Wind Project
Onshore wind
33.0 MWOperating Franklin, MEISO-NE Dec 2008target 2015
Riley-Jay-Otis-Livermore
Hydro
28.3 MWOperating Androscoggin, MEISO-NE Feb 2020target 2023
Rollins Wind (Stetson Wind Phase II)
Onshore wind
27.8 MWOperating Penobscot, MEISO-NE Nov 2006target 2009
Dundee Wind
Onshore wind
27.0 MWOperating Penobscot, MEISO-NE Oct 2007target 2011
Verso Androscoggin Energy Cogen 1, 2, & 3 Increase
Gas
26.0 MWOperating Franklin, MEISO-NE May 2010target 2012
Bucksport G5
Other
25.0 MWOperating Hancock, MEISO-NE Oct 2010target 2012
Stetson Wind II(Jimmey & Owl Mt.-UPC) See # 249
Onshore wind
24.0 MWOperating Washington, MEISO-NE Jan 2008target 2010
Mousam River Solar
Solar
20.0 MWOperating York, MEISO-NE Aug 2019target 2025
Silver Maple Wind
Onshore wind
20.0 MWOperating Penobscot, MEISO-NE May 2017target 2022
Solar
Solar
20.0 MWOperating Androscoggin, MEISO-NE Sep 2019target 2024
Milo Solar
Solar
20.0 MWOperating Piscataquis, MEISO-NE Mar 2019target 2021
Canton Mountain Winds
Onshore wind
19.3 MWOperating Oxford, MEISO-NE May 2009target 2017
Spruce Mountain Wind
Onshore wind
18.0 MWOperating Oxford, MEISO-NE Jan 2009target 2010
Casco Bay Energy Storage
Battery storage
16.2 MWOperating Cumberland, MEISO-NE Nov 2015target 2016
Red Shield Acquisition - Biomass
Other
16.0 MWOperating Penobscot, MEISO-NE Jan 2009target 2009
Georgia Pacific
Other
16.0 MWOperating Penobscot, MEISO-NE Feb 2005target 2005
Red Shield( Georgia Pacific/Old Town)
Other
16.0 MWOperating Penobscot, MEISO-NE Nov 2006target 2006
RoxWind
Onshore wind
15.3 MWOperating Oxford, MEISO-NE Jun 2017target 2021
Weston Station AVR Replacement U2-4
Hydro
14.8 MWOperating Somerset, MEISO-NE Feb 2012target 2015
Bowman Street 115 kV SS - Augusta Area Study
Solar + storage
9.9 MWOperating Kennebec, MEISO-NE Oct 2020target 2022
Bowman Street 115 kV SS - Augusta Area Study
Solar + storage
9.5 MWOperating Kennebec, MEISO-NE Oct 2020target 2023
Westbrook Energy Center Expansion
Gas
9.5 MWOperating York, MEISO-NE Jan 2012target 2013
Red Shield Acquisition #5
Gas
9.5 MWOperating Penobscot, MEISO-NE Nov 2009target 2010
Pisgah Mountain
Onshore wind
9.0 MWOperating Penobscot, MEISO-NE Oct 2010target 2016
Rumford Uprate and Battery addition
Other
8.5 MWOperating Oxford, MEISO-NE Mar 2021target 2023
ND OTM LLC Generator Reactivation
Other
8.0 MWOperating Penobscot, MEISO-NE Dec 2019target 2021
Bonny Eagle Energy Storage - Uprate
Other
8.0 MWOperating York, MEISO-NE Mar 2021target 2023
Solar
Solar
7.2 MWOperating Kennebec, MEISO-NE Aug 2019target 2021
Solar
Solar
4.8 MWOperating York, MEISO-NE Aug 2019target 2022
Solar
Solar
4.6 MWOperating Oxford, MEISO-NE Aug 2019target 2021
Solar
Solar
4.6 MWOperating Oxford, MEISO-NE Aug 2019target 2021
Gulf Island Unit 2 Increase
Hydro
4.4 MWOperating Androscoggin, MEISO-NE Dec 2010target 2011
Augusta E. Side 115 kV SS - Augusta Area Study
Solar + storage
4.3 MWOperating Kennebec, MEISO-NE Oct 2020target 2022
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)