BATTERY STORAGE · ISO-NE

Casco Bay Energy Storage

Casco Bay Energy Storage is a 16.2 MW battery storage request built and operating in the ISO-NE interconnection queue, in Cumberland County, Maine.

Queue statusOperating
  1. PlanningQueued Nov 2015 (completed)
  2. ConsentedSep 2017 (completed)
  3. Construction (completed)
  4. OperatingTarget Dec 2016 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
575
Grid region
ISO-NE (New England)
Connection point (POI)
CMP''s PTF 115kV Upper Bus at William F Wyman Station
Location
Cumberland County, Maine
Technology
Battery: 16.2 MW
Total requested
16.2 MW
Service type
Energy only (ERIS)
Study phase
Executed
Queue status
Operational
Entered queue
3 November 2015
Agreement signed
14 September 2017
Proposed online date
December 2016

Location

Marker shows the centre of Cumberland County; the queue data does not give exact sites.