United States › Grid › Interconnection queues › Maine
SOLAR · ISO-NERaymond 115 kV SS - Raymond Area DG Study
Raymond 115 kV SS - Raymond Area DG Study is a 9.9 MW solar request withdrawn in the ISO-NE interconnection queue, in Cumberland County, Maine, connecting to CMP.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2023 (completed)
- Withdrawn / abandonedJun 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 1446
- Grid region
- ISO-NE (New England)
- Utility / transmission owner
- CMP
- Connection point (POI)
- CMP Raymond 115 kV Substation
- Location
- Cumberland County, Maine
- Technology
- Solar: 9.9 MW
- Total requested
- 9.9 MW
- Queue status
- Withdrawn
- Entered queue
- 29 September 2023
- Proposed online date
- June 2025
- Withdrawn
- June 2025
Location
Marker shows the centre of Cumberland County; the queue data does not give exact sites.
Other requests in Cumberland County
- West Baldwin SolarSolar · 17.1 MW · agreement signed
- Cross Town Battery StorageBattery storage · 175 MW · built
- Casco Bay Energy StorageBattery storage · 16.2 MW · built
- Newcastle 115 kV SS - Midcoast Area DG StudySolar · 11.6 MW · withdrawn
- Battery StorageBattery storage · 10.0 MW · withdrawn
- BiomassOther · 7.6 MW · withdrawn
- Solar and BatterySolar + storage · 5.0 MW · withdrawn
- CMP Spring St 115 kV SS - Greater Portland Area DG StudySolar · 5.0 MW · withdrawn
- CMP Elm St 115 kV SS - Greater Portland Area DG StudySolar · 5.0 MW · withdrawn
- BiomassOther · 4.9 MW · withdrawn
- CMP Moshers/Prides Corner 115 kV SS - Greater Portland Area DG StudyOther · 4.0 MW · withdrawn
- CMP Vallee Lane 115 kV SS - Louden-Biddeford Area DG StudySolar · 2.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem