🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Maine

BATTERY STORAGE · ISO-NE

Battery Storage

Battery Storage is a 10.0 MW battery storage request withdrawn in the ISO-NE interconnection queue, in Cumberland County, Maine, connecting to CMP.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2019 (completed)
  2. Withdrawn / abandonedJan 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
905
Grid region
ISO-NE (New England)
Utility / transmission owner
CMP
Connection point (POI)
CMP Mussey Road substation, Circuit 636D2
Location
Cumberland County, Maine
Technology
Battery: 10.0 MW
Total requested
10.0 MW
Queue status
Withdrawn
Entered queue
1 August 2019
Proposed online date
August 2024
Withdrawn
January 2025

Location

Marker shows the centre of Cumberland County; the queue data does not give exact sites.

Power plants in Maine · Transmission lines in Maine

Other requests in Cumberland County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem