United States βΊ Grid βΊ Interconnection queues
OCTARY USA Β· INTERCONNECTION QUEUESQueue requests in study in CAISO (California) (2021 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Jove Solar Solar + storage |
4,133 MW | In study |
| Bouse Solar And Storage Plant Solar + storage |
2,021 MW | In study |
| Plum Solar + storage |
1,560 MW | In study |
| Ranegras PVS Solar + storage |
1,438 MW | In study |
| Water Rock Solar 2 Solar + storage |
1,034 MW | In study |
| Invictus Solar + storage |
860 MW | In study |
| Artemis Solar + storage |
825 MW | In study |
| Harquahala Flats 2 Solar + storage |
822 MW | In study |
| Valley Sunlight Refinery Solar + storage |
821 MW | In study |
| Solsken Solar + storage |
809 MW | In study |
| Socorro Peak Solar Solar + storage |
756 MW | In study |
| Yuha Desert Battery Storage Battery storage |
633 MW | In study |
| Cherry Lane Hybrid Solar + storage |
621 MW | In study |
| Remy Solar + storage |
617 MW | In study |
| Larrea Solar Solar + storage |
614 MW | In study |
| Soleil Cantil Solar + storage |
597 MW | In study |
| Sagebrush Energy Storage Battery storage |
528 MW | In study |
| Rosa Storage Battery storage |
512 MW | In study |
| Sterling Solar + storage |
500 MW | In study |
| Corby 2 Battery storage |
476 MW | In study |
| Mineral King Solar Solar + storage |
430 MW | In study |
| Boulder Brush Hybrid Wind + storage |
420 MW | In study |
| Tolenas Battery storage |
417 MW | In study |
| Alisa Solar Energy Complex Solar + storage |
417 MW | In study |
| Lotus Solar 2 Solar + storage |
406 MW | In study |
| Simon Battery storage |
406 MW | In study |
| Coral Reef Battery storage |
406 MW | In study |
| Fleetwood Battery storage |
406 MW | In study |
| Dirac Battery storage |
403 MW | In study |
| Brushy Battery storage |
400 MW | In study |
| Northeast Central Valley Battery storage |
365 MW | In study |
| Dandelion Hybrid Solar Solar + storage |
334 MW | In study |
| Harquahala Sunrise 2 Solar + storage |
330 MW | In study |
| Cargo Storage Battery storage |
313 MW | In study |
| Bell Bluff Storage Battery storage |
313 MW | In study |
| Harmony Storage 2 Battery storage |
308 MW | In study |
| Juniper Storage Solar + storage |
307 MW | In study |
| Gnarly Osage Battery storage |
304 MW | In study |
| Carmine Battery storage |
292 MW | In study |
| Delamar Energy Storage 2 Battery storage |
256 MW | In study |
| Almande Energy Storage Battery storage |
256 MW | In study |
| Sherman Energy Storage Battery storage |
256 MW | In study |
| Gateway Energy Storage 2 Battery storage |
256 MW | In study |
| Sandbar Energy Storage Battery storage |
256 MW | In study |
| Weston Storage Battery storage |
214 MW | In study |
| Frigatebird Storage Battery storage |
214 MW | In study |
| Phaenon Solar + storage |
204 MW | In study |
| Puma Storage Battery storage |
204 MW | In study |
| Everest Energy Storage Battery storage |
202 MW | In study |
| Merlin Storage Battery storage |
200 MW | In study |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)172 Β· 56.8 GW
- CAISO (California)70 Β· 31.5 GW
- ERCOT (Texas)116 Β· 23.2 GW
- MISO (Midcontinent)126 Β· 22.4 GW
- Southeast (non-ISO utilities)44 Β· 9,966 MW
- SPP (Southwest Power Pool)25 Β· 5,570 MW
- PJM (Mid-Atlantic, Midwest)49 Β· 2,072 MW
- NYISO (New York)11 Β· 991 MW
- ISO-NE (New England)3 Β· 525 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)