Completed queue projects in the USA — page 86

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown4,787563.7 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

4,787 requests · page 86 of 96
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project 193, Big Horn County
Solar
3.0 MWOperating Big Horn, MTWest Feb 20152016
Solar project 471, Iron County
Solar · Quichapa 1, LLC
3.0 MWOperating Iron, UTWest Feb 2013target 2016
Solar project 454, Iron County
Solar · REUT Origination, LLC
3.0 MWOperating Iron, UTWest Jan 2013target 2015
Louisa Gas Turbines Units 1 through 5
Gas
3.0 MWOperating Orange, VAPJM Nov 20082009
Onshore wind project 349, Meagher County
Onshore wind
3.0 MWOperating Meagher, MTWest Jul 20182018
Solar project 512, Baker County
Solar · Adapture Renewables
3.0 MWOperating Baker, ORWest Jan 2016target 2016
Gas project D29, Montgomery County
Gas
3.0 MWOperating Montgomery, MDPJM Jul 20002001
Essex County Correctional Facility
Gas
3.0 MWOperating Essex, NJPJM Sep 20112014
Solar project 492, Beaver County
Solar · Laho Solar, LLC
3.0 MWOperating Beaver, UTWest Mar 2013target 2015
Other project Q35, Maricopa County
Other
3.0 MWOperating Maricopa, AZWest Oct 2007target 2009
Stewarts Bridge Hydro
Hydro · Brookfield Renewable Power
3.0 MWOperating Saratoga, NYNYISO Aug 20102015
Onshore wind project 376, Elmore County
Onshore wind
3.0 MWOperating Elmore, IDWest Jun 20112012
Augusta Solar Farm
Solar
3.0 MWOperating Sussex, NJPJM Jan 20112016
Solar project 179, Lewis And Clark County
Solar
3.0 MWOperating Lewis And Clark, MTWest Jan 20152015
Solar project 489, Iron County
Solar · Cedar Valley Solar, LLC
3.0 MWOperating Iron, UTWest Mar 2013target 2015
Solar project 475, Iron County
Solar · Beryl Solar, LLC
3.0 MWOperating Iron, UTWest Mar 2013target 2015
Solar project SGI-PNM-2010-06, Bernalillo County
Solar
3.0 MWOperating Bernalillo, NMWest May 2010
Burlington Generating Station
Gas
3.0 MWOperating Burlington, NJPJM Feb 20132015
Onshore wind project 350, Meagher County
Onshore wind
3.0 MWOperating Meagher, MTWest Jul 20182018
Onshore wind project 233, Baker County
Onshore wind
3.0 MWOperating Baker, ORWest Mar 20082011
Stoltze Land and Lumber Project
Other
3.0 MWOperating Flathead, MTWest Dec 2011target 2013
Onshore wind project GI-0113, Ward County
Onshore wind
3.0 MWOperating Ward, NDWest Oct 2001
Hydro project G563, Eau Claire County
Hydro
3.0 MWOperating Eau Claire, WIMISO Nov 20052007
Solar project Q213, Yuma County
Solar
3.0 MWOperating Yuma, AZWest May 2012target 2012
Dresden Nuclear Generation Station, Units 2 & 3
Nuclear
3.0 MWOperating Grundy, ILPJM Mar 20112013
Hydro project 75, Douglas County
Hydro · PacifiCorp Energy
3.0 MWOperating Douglas, ORWest Apr 2006target 2008
Mill Run WF
Onshore wind
3.0 MWOperating Fayette, PAPJM Jul 20032005
Other project 11, Twin Falls County
Other
3.0 MWOperating Twin Falls, IDWest Mar 2001target 2002
Solar project 204, Lewis And Clark County
Solar
3.0 MWOperating Lewis And Clark, MTWest May 20152016
City of Walla Walla Mill Creek Hydroelectric
Hydro
3.0 MWOperating Walla Walla, WAWest Jun 2012target 2013
Solar project 455, Iron County
Solar · REUT Origination, LLC
3.0 MWOperating Iron, UTWest Jan 2013target 2015
GEMS Landfill Solar
Solar
3.0 MWOperating Camden, NJPJM Mar 20162022
Solar project 525, Malheur County
Solar · Adapture Renewables
3.0 MWOperating Malheur, ORWest Aug 2017target 2019
Solar project 1045, Umatilla County
Solar · Pilot Rock Solar 2, LLC
3.0 MWOperating Umatilla, ORWest Jul 2018target 2025
Onshore wind project 374, Elmore County
Onshore wind
3.0 MWOperating Elmore, IDWest Jun 20112012
Wetteland Solar Farm
Solar
3.0 MWOperating Hunterdon, NJPJM Jan 20112016
Other project 73, Marion County
Other · G2 Landfill
3.0 MWOperating Marion, FLSoutheast Oct 20072010
Onshore wind project 377, Elmore County
Onshore wind
3.0 MWOperating Elmore, IDWest Jun 20112012
Solar project 178, Golden Valley County
Solar
3.0 MWOperating Golden Valley, MTWest Jan 20152016
Other project GI-0701, Lincoln County
Other · Great Plains Ethanol
3.0 MWOperating Lincoln, SDWest Jan 2007target 2007
Stafford Regional LF
Other
3.0 MWOperating Stafford, VAPJM Aug 20072008
Solar project 510, Malheur County
Solar · Adapture Renewables
3.0 MWOperating Malheur, ORWest Jan 2016target 2016
Bernards Township Solar Farm
Solar
3.0 MWOperating Somerset, NJPJM Apr 20112016
Frenchtown 2 Solar
Solar
3.0 MWOperating Hunterdon, NJPJM Jan 20102012
Hydro project G564, Eau Claire County
Hydro
3.0 MWOperating Eau Claire, WIMISO Nov 20052007
Onshore wind project 348, Meagher County
Onshore wind
3.0 MWOperating Meagher, MTWest Jul 20182018
Solar project 464, Iron County
Solar · REUT Origination, LLC
3.0 MWOperating Iron, UTWest Feb 2013target 2015
Five Corners Substation - NG Western MA Area Cluster Study
Solar
3.0 MWOperating Hampshire, MAISO-NE Dec 2018target 2021
Qualco Project
Other
3.0 MWOperating Snohomish, WAWest Oct 2020target 2021
Solar project 473, Iron County
Solar · Quichapa 3, LLC
3.0 MWOperating Iron, UTWest Feb 2013target 2016
Page 86 of 96

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)