United States › Grid › Interconnection queues › Montana
OTHER · WESTStoltze Land and Lumber Project
Stoltze Land and Lumber Project is a 3.0 MW other request built and operating in the West interconnection queue, in Flathead County, Montana, connecting to F.H. Stoltze Land and Lumber Co..
Request details
- Queue ID
- G0468
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- F.H. Stoltze Land and Lumber Co.
- Connection point (POI)
- Flathead 12.5 kV Radial from Trumble Creek Substation.
- Location
- Flathead County, Montana
- Technology
- Other: 3.0 MW
- Total requested
- 3.0 MW
- Service type
- Energy only (ERIS)
- Study phase
- IA Executed
- Queue status
- Operational
- Entered queue
- 6 December 2011
- Agreement signed
- 12 January 2013
- Proposed online date
- October 2013
Location
Marker shows the centre of Flathead County; the queue data does not give exact sites.
Other requests in Flathead County
- Other project G0710, Flathead CountyOther · 1.6 MW · in study
- Battery storage project G1085, Flathead CountyBattery storage · 0.3 MW · in study
- Flathead LFGTE ProjectOther · 2.0 MW · built
- Whitefish In-Line Hydroelectric ProjectHydro · 1.0 MW · built
- Onshore wind project G0373, Flathead CountyOnshore wind · 200 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem